Orchard Park (5.1 MW solar farm)

Orchard Park is a 5.1 MW solar farm project in East Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 21 September 2016; the record was last updated on 4 October 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.1 MWsolar farm
refused on appealstatus in REPD
4 October 2016record last updated
East Devoncouncil area

Planning timeline

DateStage
15 December 2014Application submitted
4 December 2015Refused by the planning authority
16 March 2016Appeal lodged
21 September 2016Appeal refused

Project details

Technology
solar farm
Capacity
5.1 MW
Status (REPD)
refused on appeal
Record last updated
4 October 2016
Operator or applicant
Solstice Renewables
Planning authority
East Devon
Planning application reference
14/2952/MFUL
Appeal reference
APP/U1105/W/16/3144419
Site area
19.4 ha
Address (REPD)
Land at Shepherds farm, Oil Mill Lane, Clyst St Mary
Council area (by location)
East Devon
Time to decision
51 weeks
REPD reference
4895

Earlier applications for this site

ApplicationMWSubmittedOutcome
Orchard solar park 14/1379/MFUL7.56 June 2014refused 15 September 2014

Who decides

ApplicationsEast DevonUK
Decided applications (solar, wind, battery)5510,236
Refused17 (31%)19%
Solar refused9 of 3612%
Battery storage refused8 of 1916%
Median time from submission to decision21.0 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Higher Bagmore Farm, Ebford Lane -Battery Energy Storage Systembattery storage50application submitted2.9
Coombe Farmsolar farm8operational5.6
Higher Hawkerland Farm, Sidmouth Road Solar Farmsolar farm18approved, not built5.6
Kerswell Barton Farm, Broadclystsolar farm16.2approved, not built5.7
Blackhill Quarry, Woodburybattery storage60approved, not built5.9
Ford Oaks Solar & Green Infrastructure Facilitysolar farm30under construction6.3
Poltimore solar farmsolar farm5.5refused6.6
Burrowton Farmsolar farm5operational6.7
Great Houndbeare Farmsolar farm10operational6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7015, -3.4341).