Energy Projects Near You

National Grid Axminster Substation (49.9 MW battery storage)

National Grid Axminster Substation is a 49.9 MW battery storage project in East Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 7 September 2020, no decision recorded; the record was last updated on 30 September 2020. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
application submittedmay be out of datestatus in REPD
30 September 2020record last updated
East Devoncouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
7 September 2020Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
application submitted
Record last updated
30 September 2020
Operator or applicant
Harbour Energy
Planning authority
East Devon
Planning application reference
20/1877/FUL
Address (REPD)
National Grid Axminster Substa, Pound Road, Hawkchurch, Axminster, Devon
Council area (by location)
East Devon
REPD reference
8036

Who decides

ApplicationsEast DevonUK
Decided applications (solar, wind, battery)5510,236
Refused17 (31%)19%
Solar refused9 of 3612%
Battery storage refused8 of 1916%
Median time from submission to decision21.0 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Stonebarrow Farmsolar farm8operational<0.1
Pound Road, Hawkchurchbattery storage120refused0.3
Wareham Road, Scouse Farmbattery storage50refused0.5
Pound Road, Hawkchurchbattery storage120refused1.0
Stammery Hillbattery storage150refused1.5
Newlands Farm, Crewkerne Roadbattery storage80refused2.2
Beavor - Photovoltaic Solar Arrayssolar farm18.9under construction2.2
Newlands Farm (East Devon)solar farm5operational2.4
Axe View Solar Farmsolar farm5operational3.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7858, -2.9246).