Energy Projects Near You

Axe View Solar Farm (5 MW)

Axe View Solar Farm is a 5 MW solar farm project in East Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 March 2017; the record was last updated on 2 March 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
2 March 2018record last updated
East Devoncouncil area

Planning timeline

DateStage
24 March 2015Application submitted
5 November 2015Refused by the planning authority
19 January 2016Appeal lodged
15 April 2016Planning permission granted
15 April 2016Appeal allowed
15 January 2017Construction started
15 March 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
2 March 2018
Operator or applicant
NESF (formerly INRG Solar)
Planning authority
East Devon
Planning application reference
15/0645/MFUL
Appeal reference
APP/U1105/W/16/3141816
Site area
9.5 ha
Address (REPD)
Land East Of Wadbrook Farm, Wadbrook, Axminster,
Council area (by location)
East Devon
Time to decision
55 weeks
REPD reference
5131

Recorded together with Axe View Solar Farm, Wadbrook (battery storage, approved, not built).

Who decides

ApplicationsEast DevonUK
Decided applications (solar, wind, battery)5510,236
Refused17 (31%)19%
Solar refused9 of 3612%
Battery storage refused8 of 1916%
Median time from submission to decision21.0 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Pound Road, Hawkchurchbattery storage120refused3.3
Wareham Road, Scouse Farmbattery storage50refused3.4
Coombe Farmbattery storage7.5permission expired3.6
JB Wheatonbattery storage8.8operational3.7
Pound Road, Hawkchurchbattery storage120refused3.7
National Grid Axminster Substationbattery storage49.9application submitted3.8
Stonebarrow Farmsolar farm8operational3.8
Beavor - Photovoltaic Solar Arrayssolar farm18.9under construction3.8
Stammery Hillbattery storage150refused4.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8117, -2.959).