Solar, wind and battery projects near Lyme Regis (DT7)
16 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DT7 (Dorset): 1 is waiting for a planning decision, 4 approved but not yet running, 5 operational. The largest live scheme is National Grid Axminster Substation (49.9 MW battery storage, application submitted on 7 September 2020, no decision recorded; REPD status may be out of date), 6.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of DT7
Projects of 1 MW and more (12)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Newlands Farm (East Devon)solar farm | solar farm | 5 | operationalupdated Apr 2013 | Jul 2012 | granted Nov 2012 | Apr 2013 | East Devon | 4.8 |
| Newlands Farm, Crewkerne Roadbattery storage | battery storage | 80 | refusedupdated Oct 2025 | Dec 2024 | refused Sep 2025 | Oct 2025 | East Devon | 4.9 |
| Beavor - Photovoltaic Solar Arrayssolar farm | solar farm | 18.9 | under constructionupdated Mar 2023 | Nov 2021 | granted Feb 2022 | Mar 2023 | East Devon | 5.4 |
| Stammery Hillbattery storage | battery storage | 150 | refusedupdated Jun 2025 | Jun 2024 | refused May 2025 | Jun 2025 | East Devon | 5.4 |
| Wyld Meadow Solar Farmsolar farm | solar farm | 4.8 | operationalupdated Jul 2018 | Apr 2011 | granted Jul 2011 | Jul 2018 | East Devon | 5.6 |
| Stonebarrow Farmsolar farm | solar farm | 8 | operationalupdated Aug 2014 | Nov 2012 | granted Apr 2013 | Aug 2014 | East Devon | 6.4 |
| Wareham Road, Scouse Farmbattery storage | battery storage | 50 | refusedupdated Jul 2025 | Oct 2024 | refused Jun 2025 | Jul 2025 | East Devon | 6.5 |
| National Grid Axminster Substationbattery storage | battery storage | 49.9 | application submitted may be out of dateupdated Sep 2020 | Sep 2020 | — | Sep 2020 | East Devon | 6.5 |
| Pound Road, Hawkchurchbattery storage | battery storage | 120 | refusedupdated Oct 2022 | Oct 2022 | refused Feb 2024 | Oct 2022 | East Devon | 6.7 |
| Beechgrove Farmsolar farm | solar farm | 4 | operationalupdated Oct 2013 | Mar 2011 | granted May 2011 | Oct 2013 | East Devon | 7.0 |
| Pound Road, Hawkchurchbattery storage | battery storage | 120 | refusedupdated Aug 2023 | May 2023 | refused Aug 2023 | Aug 2023 | East Devon | 7.5 |
| Axe View Solar Farmsolar farm | solar farm | 5 | operationalupdated Mar 2018 | Mar 2015 | granted Apr 2016 | Mar 2018 | East Devon | 9.2 |
Smaller schemes under 1 MW, mostly rooftop solar (4)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Wyld Meadow Farmbattery storage | battery storage | — | approved, not built may be out of dateupdated May 2022 | May 2022 | granted Jul 2022 | May 2022 | East Devon | 5.9 |
| Hawkchurchbattery storage | battery storage | — | refusedupdated Sep 2025 | Mar 2022 | refused Aug 2025 | Sep 2025 | East Devon | 7.5 |
| Golden Cap Holiday Park, Seatownsolar farm | solar farm | 0.3 | approved, not built may be out of dateupdated May 2023 | Nov 2022 | granted May 2023 | May 2023 | Dorset | 8.8 |
| Axe View Solar Farm, Wadbrookbattery storage | battery storage | — | approved, not built may be out of dateupdated Apr 2022 | Mar 2022 | granted Mar 2023 | Apr 2022 | East Devon | 9.2 |
Distance from the average position of the DT7 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 7 | 0 | 2 | 5 | 0 | 19.2 |
| Battery storage | 9 | 1 | 2 | 0 | 6 | 49.9 |
MW in pipeline: pending, approved and under-construction capacity.
How Dorset decides solar, wind and battery applications
| Applications | Dorset | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 125 | 10,236 |
| Refused | 23 (18%) | 19% |
| Solar refused | 15 of 105 | 12% |
| Onshore wind refused | 5 of 5 | 45% |
| Battery storage refused | 3 of 15 | 16% |
| Median time from submission to decision | 19.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 6 / 6 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DT7, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.