Energy Projects Near You

Solar, wind and battery projects near Bridport (DT6)

6 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DT6 (Dorset): 6 approved but not yet running. The largest live scheme is Golden Cap Holiday Park, Seatown (0.3 MW solar farm, approved on 3 May 2023, not yet built; REPD status may be out of date), 3.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6projects within 10 km
0awaiting a decision
6approved, not running
0operational

Projects within 10 km of DT6

Smaller schemes under 1 MW, mostly rooftop solar (6)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Atrim Road, Dotterysolar farmsolar farm0.2approved, not built may be out of dateupdated Mar 2023Sep 2022granted Feb 2023Mar 2023Dorset1.8
Highlands End Holiday Park, Highlands End -Solar PV Panelssolar farmsolar farm0.2approved, not builtupdated Nov 2023Feb 2023granted Oct 2023Nov 2023Dorset2.0
Bridec Melamine Boards, West Bay Roadrooftop solarrooftop solar0.2approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Dorset3.1
Golden Cap Holiday Park, Seatownsolar farmsolar farm0.3approved, not built may be out of dateupdated May 2023Nov 2022granted May 2023May 2023Dorset3.7
Burton Bradstock Solar Panelsrooftop solarrooftop solar—under constructionupdated Jan 2021Oct 2020granted Jan 2021Jan 2021Dorset3.9
Copse Barn, Wytherston Farmrooftop solarrooftop solar0.1approved, not builtupdated Aug 2024Jun 2023granted Jul 2024Aug 2024Dorset8.5

Distance from the average position of the DT6 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm303000.7
Rooftop solar303000.3

MW in pipeline: pending, approved and under-construction capacity.

How Dorset decides solar, wind and battery applications

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

All projects in Dorset

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DT6, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.