Pound Road, Hawkchurch (120 MW battery storage, 2022 application)

Pound Road, Hawkchurch is a 120 MW battery storage project in East Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 16 February 2024; the record was last updated on 19 October 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

120 MWbattery storage
refusedstatus in REPD
19 October 2022record last updated
East Devoncouncil area

Planning timeline

DateStage
5 October 2022Application submitted
16 February 2024Refused by the planning authority

Project details

Technology
battery storage (stand-alone storage)
Capacity
120 MW
Status (REPD)
refused
Record last updated
19 October 2022
Operator or applicant
Enso Green Holdings B Limited
Planning authority
East Devon
Planning application reference
22/2216/MFUL
Address (REPD)
Pound Road, Ne/O Axminster National Grid Substation Pound Road, Hawkchurch, Axminster
Council area (by location)
East Devon
Time to decision
71 weeks
Name in REPD
Pound Road, Hawkchurch - Battery Energy Storage
REPD reference
12360

Who decides

ApplicationsEast DevonUK
Decided applications (solar, wind, battery)5510,236
Refused17 (31%)19%
Solar refused9 of 3612%
Battery storage refused8 of 1916%
Median time from submission to decision21.0 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
National Grid Axminster Substationbattery storage49.9application submitted0.3
Stonebarrow Farmsolar farm8operational0.3
Wareham Road, Scouse Farmbattery storage50refused0.7
Pound Road, Hawkchurchbattery storage120refused0.7
Stammery Hillbattery storage150refused1.8
Newlands Farm, Crewkerne Roadbattery storage80refused2.4
Beavor - Photovoltaic Solar Arrayssolar farm18.9under construction2.4
Newlands Farm (East Devon)solar farm5operational2.6
Gashay Lanesolar farm5refused3.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7879, -2.9223).