Energy Projects Near You

Lee Moor China Clay Works (9.5 MW solar farm)

Lee Moor China Clay Works is a 9.5 MW solar farm project in South Hams, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 December 2015; the record was last updated on 20 October 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.5 MWsolar farm
operationalstatus in REPD
20 October 2016record last updated
South Hamscouncil area

Planning timeline

DateStage
6 August 2014Application submitted
27 October 2014Planning permission granted
15 August 2015Construction started
15 December 2015Operational

Project details

Technology
solar farm
Capacity
9.5 MW
Status (REPD)
operational
Record last updated
20 October 2016
Operator or applicant
Wanageeska
Planning authority
South Hams
Planning application reference
DCC/3689/2014
Address (REPD)
Portworthy Dams 2 and 3, Lee Moor China Clay Works, Lee Moor
Council area (by location)
South Hams
Time to decision
12 weeks
REPD reference
4839

Who decides

ApplicationsSouth HamsUK
Decided applications (solar, wind, battery)3610,236
Refused6 (17%)19%
Solar refused3 of 2812%
Onshore wind refused3 of 345%
Battery storage refused0 of 516%
Median time from submission to decision13.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Newnham Estatesolar farm14operational4.5
Langage Solar Farmsolar farm5operational6.5
Chelson Meadow Solar Farmsolar farm13approved, not built9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.4472, -4.0131).