Solar, wind and battery projects near Torpoint (PL11)
28 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PL11 (Cornwall): 2 are waiting for a planning decision, 12 approved but not yet running, 11 operational. The largest live scheme is West Kingsmill, Landulph (80 MW battery storage, approved on 18 July 2025, not yet built), 7.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of PL11
Projects of 1 MW and more (18)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Trevol Business Parkbattery storage | battery storage | 10 | approved, not built may be out of dateupdated Jan 2020 | Apr 2019 | granted Sep 2019 | Jan 2020 | Cornwall | 2.1 |
| Mendennick Wind Farmwind farm | wind farm | 2.6 | application withdrawnupdated May 2013 | Jan 2013 | — | May 2013 | Cornwall | 2.2 |
| Mendennick Farmsolar farm | solar farm | 2.8 | operationalupdated Jul 2017 | Nov 2014 | granted Feb 2015 | Jul 2017 | Cornwall | 2.3 |
| Anthony Estate Solar Farmsolar farm | solar farm | 4.7 | operationalupdated Oct 2015 | Jul 2014 | granted Dec 2014 | Oct 2015 | Cornwall | 2.6 |
| Southdown Quarrysolar farm | solar farm | 1.5 | operationalupdated Dec 2015 | Jul 2014 | granted Oct 2014 | Dec 2015 | Cornwall | 4.2 |
| Ernesettle Solar Farmsolar farm | solar farm | 4.1 | operationalupdated May 2016 | Jul 2015 | granted Sep 2015 | May 2016 | Plymouth | 6.8 |
| Landulph Substation, Landulphbattery storage | battery storage | 99.9 | application withdrawnupdated Jul 2024 | Jan 2024 | — | Jul 2024 | Cornwall | 7.6 |
| West Kingsmill, Landulphbattery storage | battery storage | 80 | approved, not builtupdated Aug 2025 | Dec 2024 | granted Jul 2025 | Aug 2025 | Cornwall | 7.6 |
| West Kingsmill Farm Solar Parksolar farm | solar farm | 1.6 | operationalupdated Oct 2014 | Feb 2011 | granted May 2011 | Oct 2014 | Cornwall | 7.7 |
| Land At Lanthronesolar farm | solar farm | 5 | refusedupdated Apr 2013 | Jun 2012 | refused Jan 2013 | Apr 2013 | Cornwall | 7.8 |
| Land At Bake Farmsolar farm | solar farm | 5 | operationalupdated Jun 2016 | Jun 2015 | granted Sep 2015 | Jun 2016 | Cornwall | 7.8 |
| Howton Farmsolar farm | solar farm | 4.4 | operationalupdated Jul 2011 | Jan 2011 | granted Apr 2011 | Jul 2011 | Cornwall | 7.9 |
| North Wayton Farmsolar farm | solar farm | 5 | operationalupdated Sep 2015 | Oct 2012 | granted Apr 2013 | Sep 2015 | Cornwall | 8.1 |
| Landulph, Ellbridge Lanebattery storage | battery storage | 49.9 | approved, not built may be out of dateupdated Feb 2023 | Nov 2022 | granted Feb 2023 | Feb 2023 | Cornwall | 8.3 |
| Landulph Substation, Ellbridge Lanebattery storage | battery storage | 49.9 | approved, not builtupdated Sep 2023 | Mar 2023 | granted Sep 2023 | Sep 2023 | Cornwall | 8.3 |
| Wilton Farm (pv)solar farm | solar farm | 9.5 | operationalupdated Jun 2015 | Jan 2013 | granted Jan 2014 | Jun 2015 | Cornwall | 9.3 |
| Warleigh Barton Solar Farmsolar farm | solar farm | 5 | operationalupdated Apr 2013 | Jun 2011 | granted Nov 2012 | Apr 2013 | Plymouth | 9.5 |
| Trequite Farm solar parksolar farm | solar farm | 9.9 | operationalupdated Oct 2014 | May 2013 | granted Aug 2013 | Oct 2014 | Cornwall | 9.8 |
Smaller schemes under 1 MW, mostly rooftop solar (10)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Spinnaker International Spinnaker House, Long Acrerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2023 | Oct 2023 | granted Dec 2023 | Dec 2023 | Cornwall | 4.9 |
| Battery Box - Birch House - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Jan 2024 | Nov 2023 | granted Jan 2024 | Jan 2024 | Cornwall | 5.1 |
| China Fleet Country Clubsolar farm | solar farm | 0.6 | approved, not builtupdated Feb 2025 | Oct 2024 | granted Dec 2024 | Feb 2025 | Cornwall | 5.4 |
| China Fleet Country Club, Pill Lanesolar farm | solar farm | 0.6 | application submittedupdated Sep 2025 | Oct 2024 | — | Sep 2025 | Cornwall | 5.8 |
| Princess Yachts Limitedrooftop solar | rooftop solar | 0.7 | under constructionupdated Aug 2021 | Jul 2021 | — | Aug 2021 | Plymouth | 6.6 |
| Kawasaki Factory, Ernesettle Lanerooftop solar | rooftop solar | — | approved, not builtupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Plymouth | 7.2 |
| Plymouth Marine Laboratory, Prospect Placerooftop solar | rooftop solar | 0.1 | approved, not built may be out of dateupdated Mar 2023 | Jan 2023 | granted Mar 2023 | Mar 2023 | Plymouth | 7.7 |
| Armada Way Solar panelsrooftop solar | rooftop solar | — | approved, not built may be out of dateupdated Feb 2022 | Jan 2021 | granted Apr 2021 | Feb 2022 | Plymouth | 8.0 |
| Council Houserooftop solar | rooftop solar | — | approved, not built may be out of dateupdated Mar 2022 | Jan 2021 | granted Mar 2021 | Mar 2022 | Plymouth | 8.0 |
| Interfish, Wallsend Industrial Estatesolar farm | solar farm | 0.2 | application submitted | Jun 2026 | — | — | Plymouth | 9.7 |
Distance from the average position of the PL11 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 15 | 2 | 1 | 11 | 1 | 1.4 |
| Rooftop solar | 6 | 0 | 6 | 0 | 0 | 1 |
| Wind farm | 1 | 0 | 0 | 0 | 0 | 0 |
| Battery storage | 6 | 0 | 5 | 0 | 0 | 190 |
MW in pipeline: pending, approved and under-construction capacity.
How Cornwall decides solar, wind and battery applications
| Applications | Cornwall | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 225 | 10,236 |
| Refused | 49 (22%) | 19% |
| Solar refused | 31 of 159 | 12% |
| Onshore wind refused | 15 of 39 | 45% |
| Battery storage refused | 3 of 27 | 16% |
| Median time from submission to decision | 16.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 23 / 20 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PL11, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.