Energy Projects Near You

Trequite Farm solar park (9.9 MW)

Trequite Farm solar park is a 9.9 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2014; the record was last updated on 1 October 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.9 MWsolar farm
operationalstatus in REPD
1 October 2014record last updated
Cornwallcouncil area

Planning timeline

DateStage
24 May 2013Application submitted
22 August 2013Planning permission granted
31 March 2014Operational

Project details

Technology
solar farm
Capacity
9.9 MW
Status (REPD)
operational
Record last updated
1 October 2014
Operator or applicant
Elgin Energy EsCo
Planning authority
Cornwall
Planning application reference
PA13/04650
Site area
23.8 ha
Address (REPD)
Land at Trequite Farm, Menheniot, Liskeard
Council area (by location)
Cornwall
Time to decision
13 weeks
REPD reference
2129

Earlier applications for this site

ApplicationMWSubmittedOutcome
Trequite Farm PA13/0224211.422 March 2013withdrawn 23 May 2013

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Trehawke Barton (Doddycross) Solar Farmsolar farm10.6operational1.4
Land At Lanthronesolar farm5refused2.2
Land At Bake Farmsolar farm5operational2.8
Wilton Farm (pv)solar farm9.5operational2.9
Ford Farm Solar Farmsolar farm5operational6.0
Newton Ferrers solar parksolar farm19.5operational6.4
Pensipple Farmsolar farm5operational6.5
Dunstan Lodge solar farmsolar farm8.5refused7.5
Landulph, Ellbridge Lanebattery storage49.9approved, not built8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.4263, -4.3656).