Land At Bake Farm (5 MW solar farm)

Land At Bake Farm is a 5 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2016; the record was last updated on 17 June 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
17 June 2016record last updated
Cornwallcouncil area

Planning timeline

DateStage
19 June 2015Application submitted
1 September 2015Planning permission granted
21 January 2016Construction started
31 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
17 June 2016
Operator or applicant
Murex Energy
Planning authority
Cornwall
Planning application reference
PA15/04793
Site area
6.9 ha
Address (REPD)
Land At Bake Farm, Bake Lane, Trerulefoot, Saltash, Cornwall
Council area (by location)
Cornwall
Time to decision
11 weeks
REPD reference
5485

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wilton Farm (pv)solar farm9.5operational1.6
Land At Lanthronesolar farm5refused2.7
Trequite Farm solar parksolar farm9.9operational2.8
Trehawke Barton (Doddycross) Solar Farmsolar farm10.6operational4.1
Pensipple Farmsolar farm5operational6.8
Newton Ferrers solar parksolar farm19.5operational8.5
Ford Farm Solar Farmsolar farm5operational8.8
Landulph, Ellbridge Lanebattery storage49.9approved, not built9.1
Landulph Substation, Landulphbattery storage99.9application withdrawn9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.4018, -4.3562).