Energy Projects Near You

Ford Farm Solar Farm (5 MW)

Ford Farm Solar Farm is a 5 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 2 May 2013; the record was last updated on 27 March 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
27 March 2014record last updated
Cornwallcouncil area

Planning timeline

DateStage
16 July 2012Application submitted
5 October 2012Planning permission granted
2 May 2013Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
27 March 2014
Operator or applicant
Ford Farm PV Scheme LLP
Planning authority
Cornwall
Planning application reference
PA12/06666
Site area
10.6 ha
Address (REPD)
Ford Farm, St Ive, Liskeard, Cornwall
Council area (by location)
Cornwall
Time to decision
12 weeks
REPD reference
1626

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Newton Ferrers solar parksolar farm19.5operational4.4
Callington Solar Farmsolar farm6.4operational4.8
Trehawke Barton (Doddycross) Solar Farmsolar farm10.6operational4.9
Trequite Farm solar parksolar farm9.9operational6.0
Dunstan Lodge solar farmsolar farm8.5refused6.3
Land At Lanthronesolar farm5refused7.1
Trefinnick Farmsolar farm5operational7.3
Wilton Farm (pv)solar farm9.5operational8.7
Land At Bake Farmsolar farm5operational8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.4796, -4.3783).