Ford Farm Solar Farm (5 MW)
Ford Farm Solar Farm is a 5 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 2 May 2013; the record was last updated on 27 March 2014.
5 MWsolar farm
operationalstatus in REPD
27 March 2014record last updated
Cornwallcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 16 July 2012 | Application submitted |
| 5 October 2012 | Planning permission granted |
| 2 May 2013 | Operational |
Project details
- Technology
- solar farm
- Capacity
- 5 MW
- Status (REPD)
- operational
- Record last updated
- 27 March 2014
- Operator or applicant
- Ford Farm PV Scheme LLP
- Planning authority
- Cornwall
- Planning application reference
- PA12/06666
- Site area
- 10.6 ha
- Address (REPD)
- Ford Farm, St Ive, Liskeard, Cornwall
- Council area (by location)
- Cornwall
- Time to decision
- 12 weeks
- REPD reference
- 1626
Who decides
| Applications | Cornwall | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 225 | 10,236 |
| Refused | 49 (22%) | 19% |
| Solar refused | 31 of 159 | 12% |
| Onshore wind refused | 15 of 39 | 45% |
| Battery storage refused | 3 of 27 | 16% |
| Median time from submission to decision | 16.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 23 / 20 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Newton Ferrers solar park | solar farm | 19.5 | operational | 4.4 |
| Callington Solar Farm | solar farm | 6.4 | operational | 4.8 |
| Trehawke Barton (Doddycross) Solar Farm | solar farm | 10.6 | operational | 4.9 |
| Trequite Farm solar park | solar farm | 9.9 | operational | 6.0 |
| Dunstan Lodge solar farm | solar farm | 8.5 | refused | 6.3 |
| Land At Lanthrone | solar farm | 5 | refused | 7.1 |
| Trefinnick Farm | solar farm | 5 | operational | 7.3 |
| Wilton Farm (pv) | solar farm | 9.5 | operational | 8.7 |
| Land At Bake Farm | solar farm | 5 | operational | 8.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.4796, -4.3783).