Energy Projects Near You

Callington Solar Farm (6.4 MW)

Callington Solar Farm is a 6.4 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 17 January 2014; the record was last updated on 22 May 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.4 MWsolar farm
operationalstatus in REPD
22 May 2014record last updated
Cornwallcouncil area

Planning timeline

DateStage
7 February 2011Application submitted
26 September 2011Planning permission granted
17 January 2014Operational

Project details

Technology
solar farm
Capacity
6.4 MW
Status (REPD)
operational
Record last updated
22 May 2014
Operator or applicant
Inazin (Low Carbon Solar)
Planning authority
Cornwall
Planning application reference
PA11/00774
Site area
17.4 ha
Address (REPD)
Land At Haye Lane, Callington, Cornwall
Council area (by location)
Cornwall
Time to decision
33 weeks
REPD reference
1564

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Newton Ferrers solar parksolar farm19.5operational3.7
Trefinnick Farmsolar farm5operational4.2
Dunstan Lodge solar farmsolar farm8.5refused4.5
Ford Farm Solar Farmsolar farm5operational4.8
Landulph, Ellbridge Lanebattery storage49.9approved, not built8.6
Trehawke Barton (Doddycross) Solar Farmsolar farm10.6operational8.8
Landulph Substation, Ellbridge Lanebattery storage49.9approved, not built8.9
Trequite Farm solar parksolar farm9.9operational9.4
Landulph Substation, Landulphbattery storage99.9application withdrawn9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.5072, -4.326).