Newton Ferrers solar park (19.5 MW)

Newton Ferrers solar park is a 19.5 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 29 March 2016; the record was last updated on 25 April 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19.5 MWsolar farm
operationalstatus in REPD
25 April 2016record last updated
Cornwallcouncil area

Planning timeline

DateStage
7 May 2014Application submitted
1 August 2014Planning permission granted
1 January 2016Construction started
29 March 2016Operational

Project details

Technology
solar farm
Capacity
19.5 MW
Status (REPD)
operational
Record last updated
25 April 2016
Operator or applicant
Gruene Energien
Planning authority
Cornwall
Planning application reference
PA14/04185
Site area
31.1 ha
Address (REPD)
Land In Newton Ferrers Callington Cornwall
Council area (by location)
Cornwall
Time to decision
12 weeks
REPD reference
2125

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dunstan Lodge solar farmsolar farm8.5refused1.9
Callington Solar Farmsolar farm6.4operational3.7
Ford Farm Solar Farmsolar farm5operational4.4
Landulph, Ellbridge Lanebattery storage49.9approved, not built5.6
Land At Lanthronesolar farm5refused6.0
Landulph Substation, Ellbridge Lanebattery storage49.9approved, not built6.0
Trehawke Barton (Doddycross) Solar Farmsolar farm10.6operational6.1
Trequite Farm solar parksolar farm9.9operational6.4
West Kingsmill, Landulphbattery storage80approved, not built6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.4741, -4.3163).