Bodrawl Farm Solar Park (7.5 MW)
Bodrawl Farm Solar Park is a 7.5 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 7 June 2013; the record was last updated on 24 July 2013.
7.5 MWsolar farm
application withdrawnstatus in REPD
24 July 2013record last updated
Cornwallcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 24 April 2013 | Application submitted |
| 7 June 2013 | Application withdrawn |
Project details
- Technology
- solar farm
- Capacity
- 7.5 MW
- Status (REPD)
- application withdrawn
- Record last updated
- 24 July 2013
- Operator or applicant
- Kinetic Energy Ltd
- Planning authority
- Cornwall
- Planning application reference
- PA13/03107
- Address (REPD)
- Bodrawl Farm East Taphouse Liskeard Cornwall
- Council area (by location)
- Cornwall
- REPD reference
- 1111
Who decides
| Applications | Cornwall | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 225 | 10,236 |
| Refused | 49 (22%) | 19% |
| Solar refused | 31 of 159 | 12% |
| Onshore wind refused | 15 of 39 | 45% |
| Battery storage refused | 3 of 27 | 16% |
| Median time from submission to decision | 16.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 23 / 20 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Langunnett Solar Farm | solar farm | 6.2 | operational | 6.0 |
| Pensipple Farm | solar farm | 5 | operational | 6.7 |
| Polmaugan Farm | solar farm | 5 | operational | 8.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.4311, -4.5385).