Langunnett Solar Farm (6.2 MW)

Langunnett Solar Farm is a 6.2 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 28 March 2013; the record was last updated on 29 September 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.2 MWsolar farm
operationalstatus in REPD
29 September 2015record last updated
Cornwallcouncil area

Planning timeline

DateStage
20 March 2012Application submitted
30 July 2012Planning permission granted
14 January 2013Construction started
28 March 2013Operational

Project details

Technology
solar farm
Capacity
6.2 MW
Status (REPD)
operational
Record last updated
29 September 2015
Operator or applicant
Vogt Solar
Planning authority
Cornwall
Planning application reference
PA12/02354
Site area
9.9 ha
Address (REPD)
Langunnett Farm, St Veep, Lostwithiel
Council area (by location)
Cornwall
Time to decision
19 weeks
REPD reference
1230

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bodrawl Farm Solar Parksolar farm7.5application withdrawn6.0
Polmaugan Farmsolar farm5operational6.4
Rew Farm Solar Farmsolar farm6.1operational7.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.3913, -4.596).