Energy Projects Near You

Burthy Row Farm, Trefullock Moor Solar Farm & Battery Storage (49.9 MW)

Burthy Row Farm, Trefullock Moor Solar Farm & Battery Storage is a 49.9 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 22 March 2023, no decision recorded; the record was last updated on 5 April 2023. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
application submittedmay be out of datestatus in REPD
5 April 2023record last updated
Cornwallcouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
22 March 2023Application submitted

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
application submitted
Record last updated
5 April 2023
Operator or applicant
JBM Solar Projects Limited
Planning authority
Cornwall
Planning application reference
PA23/01893
Site area
82.8 ha
Address (REPD)
South West Of Burthy Row Farm Trefullock Moor Summercourt
Council area (by location)
Cornwall
Contracts for Difference
AR6
Name in REPD
Burthy Row Farm, Trefullock Moor - Solar Farm & Battery Storage
REPD reference
12852

The scheme also includes battery storage, recorded separately in REPD (application submitted).

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Trefullock Solar Farmsolar farm5operational1.7
Burthy Farmsolar farm10operational1.7
Scarcewater Tipwind farm6.9refused on appeal3.2
Kernick Mica Dam Solar Farmsolar farm12operational3.3
Indian Queens Sub station, Carne Hillbattery storage50approved, not built3.3
Indian Queens Sub-Stationbattery storage47.5approved, not built3.4
Indian Queens National Grid Substation, Domelick Hillbattery storage50approved, not built3.5
Hewas Solar Farmsolar farm5operational3.8
Trendeal Solar Farmsolar farm12abandoned4.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.3753, -4.936).