Trendeal Solar Farm (12 MW)

Trendeal Solar Farm is a 12 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 19 September 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWsolar farm
abandonedstatus in REPD
19 September 2017record last updated
Cornwallcouncil area

Planning timeline

DateStage
9 August 2013Application submitted
29 October 2013Planning permission granted
29 October 2019Permission expired

Project details

Technology
solar farm
Capacity
12 MW
Status (REPD)
abandoned
Record last updated
19 September 2017
Operator or applicant
Caledon Partners
Planning authority
Cornwall
Planning application reference
PA13/06612
Address (REPD)
Land Adj To Homer Downs Ladock
Council area (by location)
Cornwall
Time to decision
12 weeks
REPD reference
1760

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hewas Solar Farmsolar farm5operational1.7
Carnemough Farm Solar Parksolar farm7operational2.0
Burthy Farmsolar farm10operational2.3
Trefullock Solar Farmsolar farm5operational2.9
Scarcewater Tipwind farm6.9refused on appeal3.0
Green Acres Farm, Scarcewater Solar Farmsolar farm49.9application submitted3.2
Kernick Mica Dam Solar Farmsolar farm12operational3.8
Fair Park Solar Farmsolar farm49.9approved, not built3.8
Hendra Barns Solar Farmsolar farm15permission expired3.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.341, -4.9537).