Scarcewater Tip (6.9 MW wind farm)

Scarcewater Tip is a 6.9 MW wind farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 11 September 2017; the record was last updated on 2 October 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.9 MWwind farm
refused on appealstatus in REPD
2 October 2017record last updated
Cornwallcouncil area

Planning timeline

DateStage
21 January 2015Application submitted
17 March 2016Refused by the planning authority
30 December 2016Appeal lodged
11 September 2017Appeal refused

Project details

Technology
wind farm
Capacity
6.9 MW
Status (REPD)
refused on appeal
Record last updated
2 October 2017
Operator or applicant
REG Windpower
Planning authority
Cornwall
Planning application reference
PA15/00511
Appeal reference
APP/D0840/W/16/3158674
Turbines
3
Turbine height
93 m
Address (REPD)
Scarcewater Tip, The Square, Grampound Road, Truro, Cornwall
Council area (by location)
Cornwall
Time to decision
60 weeks
REPD reference
4979

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kernick Mica Dam Solar Farmsolar farm12operational0.8
Green Acres Farm, Scarcewater Solar Farmsolar farm49.9application submitted1.3
Hewas Solar Farmsolar farm5operational1.5
Carnemough Farm Solar Parksolar farm7operational2.3
Burthy Farmsolar farm10operational2.6
Carloggas Farm Solar Parksolar farm8.3operational2.7
Trendeal Solar Farmsolar farm12abandoned3.0
Burthy Row Farm, Trefullock Moor Solar Farm & Battery Storagesolar farm49.9application submitted3.2
Trefullock Solar Farmsolar farm5operational3.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.3503, -4.9139).