Energy Projects Near You

Carnemough Farm Solar Park (7 MW)

Carnemough Farm Solar Park is a 7 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2016; the record was last updated on 21 June 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWsolar farm
operationalstatus in REPD
21 June 2016record last updated
Cornwallcouncil area

Planning timeline

DateStage
13 August 2013Application submitted
22 November 2013Refused by the planning authority
27 February 2015Planning permission granted
27 February 2015Appeal allowed
15 November 2015Construction started
31 March 2016Operational

Project details

Technology
solar farm
Capacity
7 MW
Status (REPD)
operational
Record last updated
21 June 2016
Operator or applicant
Elgin Energy EsCo
Planning authority
Cornwall
Planning application reference
PA13/06755
Site area
16.2 ha
Address (REPD)
Land At Carnemough Farm Grampound Road Truro Cornwall
Council area (by location)
Cornwall
Time to decision
80 weeks
REPD reference
1642

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hewas Solar Farmsolar farm5operational1.1
Green Acres Farm, Scarcewater Solar Farmsolar farm49.9application submitted1.7
Trendeal Solar Farmsolar farm12abandoned2.0
Scarcewater Tipwind farm6.9refused on appeal2.3
Kernick Mica Dam Solar Farmsolar farm12operational3.0
Burthy Farmsolar farm10operational3.5
Trefullock Solar Farmsolar farm5operational4.3
Carloggas Farm Solar Parksolar farm8.3operational4.4
Burthy Row Farm, Trefullock Moor Solar Farm & Battery Storagesolar farm49.9application submitted4.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.3316, -4.9292).