Energy Projects Near You

Solar, wind and battery projects near Newquay (TR8)

35 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TR8 (Cornwall): 2 are waiting for a planning decision, 12 approved but not yet running, 14 operational. The largest live scheme is Tregonning Farm Solar Farm & Battery Storage (68 MW solar farm, under construction since 1 May 2026), 2.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

35projects within 10 km
2awaiting a decision
12approved, not running
14operational

Projects within 10 km of TR8

Projects of 1 MW and more (30)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Hendra Holiday Park Solar Farmsolar farmsolar farm1.2operationalupdated Oct 2013Apr 2011granted Jul 2011Oct 2013Cornwall1.1
Trevemper solar farmsolar farmsolar farm1.7operationalupdated Apr 2012Jan 2011granted May 2011Apr 2012Cornwall2.2
Tregonning Farm Solar Farm & Battery Storagesolar farmsolar farm68under constructionupdated Jun 2026Mar 2022granted Dec 2023Jun 2026Cornwall2.9
Tregonning Farm Solar Farm & Battery Storagebattery storagebattery storage47.5under constructionupdated Jun 2026Mar 2022granted Dec 2023Jun 2026Cornwall2.9
Kernow Solar Farmsolar farmsolar farm5operationalupdated Sep 2018Jan 2011granted Apr 2011Sep 2018Cornwall4.0
Carines Farm Solar Arraysolar farmsolar farm1operationalupdated Apr 2013Jul 2012granted Dec 2012Apr 2013Cornwall5.4
Treworgans Wind Turbinewind turbinewind turbine2refused on appealupdated Jul 2012Mar 2010refused Aug 2011Jul 2012Cornwall5.5
Carland Cross Wind Farm - Storagebattery storagebattery storage1under constructionupdated Mar 2020Aug 2018—Mar 2020Cornwall5.5
Carland Cross Wind Farm Repoweringwind farmwind farm20operationalupdated Nov 2013Nov 2008granted Jan 2010Nov 2013Cornwall5.7
Carland Crosswind farmwind farm6decommissionedupdated Jan 2015May 1991granted Apr 1992Jan 2015Cornwall5.7
Carland Cross Solar Farmsolar farmsolar farm10under constructionupdated Dec 2021Oct 2019granted May 2020Dec 2021Cornwall6.4
Land North East Of Penrose Farsolar farmsolar farm1.5operationalupdated Dec 2015Jan 2015granted May 2015Dec 2015Cornwall6.5
Summercourt Solar Farm (Glebe Farm)solar farmsolar farm1.1operationalupdated Jun 2013Jun 2012granted Oct 2012Jun 2013Cornwall6.6
St Columb Majorbattery storagebattery storage5approved, not builtupdated Jun 2025Apr 2025granted May 2025Jun 2025Cornwall6.9
Trefullock Solar Farmsolar farmsolar farm5operationalupdated Sep 2015Oct 2010granted Jan 2011Sep 2015Cornwall7.1
Trekenning Farm Battery Storage Facility & Co-Opbattery storagebattery storage5approved, not builtupdated May 2026Nov 2022granted Dec 2025May 2026Cornwall7.3
Hendra Barns Solar Farmsolar farmsolar farm15permission expiredupdated Mar 2018Mar 2013granted Jul 2013Mar 2018Cornwall7.3
Fair Park Solar Farmsolar farmsolar farm49.9approved, not builtupdated Nov 2025Apr 2023granted Oct 2025Nov 2025Cornwall7.5
Fair Park Solar Farmbattery storagebattery storage20approved, not builtupdated Nov 2025Apr 2023granted Oct 2025Nov 2025Cornwall7.5
Burthy Row Farm, Trefullock Moor Solar Farm & Battery Storagesolar farmsolar farm49.9application submitted may be out of dateupdated Apr 2023Mar 2023—Apr 2023Cornwall8.0
Burthy Farmsolar farmsolar farm10operationalupdated May 2015Jul 2013granted Sep 2014May 2015Cornwall8.1
Goonabarn Farm Wind Turbineswind farmwind farm1operationalupdated Apr 2016Feb 2013granted Jul 2013Apr 2016Cornwall8.1
St Columb Major Solar Farmsolar farmsolar farm7operationalupdated May 2014Jan 2011granted Apr 2011May 2014Cornwall8.3
Land At Pines Tipwind farmwind farm2.7refused on appealupdated Oct 2017Feb 2015refused Mar 2016Oct 2017Cornwall8.4
Truthan Barton Wind Farmwind farmwind farm12.5refused on appealupdated Sep 2012May 2011refused Sep 2011Sep 2012Cornwall8.9
Land near Ventonteaguewind turbinewind turbine2.3operationalupdated Dec 2019Oct 2018granted Dec 2019Dec 2019Cornwall9.0
Denzell Downs Wind Farmwind farmwind farm10operationalupdated Jan 2016Jun 2013granted Dec 2013Jan 2016Cornwall9.1
Trendeal Solar Farmsolar farmsolar farm12abandonedupdated Sep 2017Aug 2013granted Oct 2013Sep 2017Cornwall9.1
Bears Down Wind Farmwind farmwind farm9.8operationalupdated Dec 2003May 2000granted Jun 2000Dec 2003Cornwall9.7
Indian Queens National Grid Substation, Domelick Hillbattery storagebattery storage50approved, not builtupdated May 2024Aug 2023granted Apr 2024May 2024Cornwall10.0
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Treloggan Roadrooftop solarrooftop solar0.4approved, not builtupdated Mar 2022Feb 2022granted Apr 2022Mar 2022Cornwall1.5
Headland Hotel, Headland Roadsolar farmsolar farm0.2refusedupdated Aug 2023Jan 2023refused Aug 2023Aug 2023Cornwall4.5
Trevornick Holiday Park, Holywell Baysolar farmsolar farm0.2approved, not built may be out of dateupdated May 2023Apr 2023granted May 2023May 2023Cornwall6.6
Burthy Row Farm, Trefullock Moor Solar Farm & Battery Storagebattery storagebattery storage—application submitted may be out of dateupdated Apr 2023Mar 2023—Apr 2023Cornwall8.0
Perransands Holiday Centre, Perransands Holiday Park Solar PV Equipmentrooftop solarrooftop solar0.5approved, not builtupdated Apr 2023Dec 2022granted Feb 2023Apr 2023Cornwall8.8

Distance from the average position of the TR8 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm171491178
Rooftop solar202000.9
Wind farm700420
Wind turbine200110
Battery storage71600128

MW in pipeline: pending, approved and under-construction capacity.

How Cornwall decides solar, wind and battery applications

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

All projects in Cornwall

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TR8, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.