Solar, wind and battery projects near Newquay (TR8)
35 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TR8 (Cornwall): 2 are waiting for a planning decision, 12 approved but not yet running, 14 operational. The largest live scheme is Tregonning Farm Solar Farm & Battery Storage (68 MW solar farm, under construction since 1 May 2026), 2.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of TR8
Projects of 1 MW and more (30)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Hendra Holiday Park Solar Farmsolar farm | solar farm | 1.2 | operationalupdated Oct 2013 | Apr 2011 | granted Jul 2011 | Oct 2013 | Cornwall | 1.1 |
| Trevemper solar farmsolar farm | solar farm | 1.7 | operationalupdated Apr 2012 | Jan 2011 | granted May 2011 | Apr 2012 | Cornwall | 2.2 |
| Tregonning Farm Solar Farm & Battery Storagesolar farm | solar farm | 68 | under constructionupdated Jun 2026 | Mar 2022 | granted Dec 2023 | Jun 2026 | Cornwall | 2.9 |
| Tregonning Farm Solar Farm & Battery Storagebattery storage | battery storage | 47.5 | under constructionupdated Jun 2026 | Mar 2022 | granted Dec 2023 | Jun 2026 | Cornwall | 2.9 |
| Kernow Solar Farmsolar farm | solar farm | 5 | operationalupdated Sep 2018 | Jan 2011 | granted Apr 2011 | Sep 2018 | Cornwall | 4.0 |
| Carines Farm Solar Arraysolar farm | solar farm | 1 | operationalupdated Apr 2013 | Jul 2012 | granted Dec 2012 | Apr 2013 | Cornwall | 5.4 |
| Treworgans Wind Turbinewind turbine | wind turbine | 2 | refused on appealupdated Jul 2012 | Mar 2010 | refused Aug 2011 | Jul 2012 | Cornwall | 5.5 |
| Carland Cross Wind Farm - Storagebattery storage | battery storage | 1 | under constructionupdated Mar 2020 | Aug 2018 | — | Mar 2020 | Cornwall | 5.5 |
| Carland Cross Wind Farm Repoweringwind farm | wind farm | 20 | operationalupdated Nov 2013 | Nov 2008 | granted Jan 2010 | Nov 2013 | Cornwall | 5.7 |
| Carland Crosswind farm | wind farm | 6 | decommissionedupdated Jan 2015 | May 1991 | granted Apr 1992 | Jan 2015 | Cornwall | 5.7 |
| Carland Cross Solar Farmsolar farm | solar farm | 10 | under constructionupdated Dec 2021 | Oct 2019 | granted May 2020 | Dec 2021 | Cornwall | 6.4 |
| Land North East Of Penrose Farsolar farm | solar farm | 1.5 | operationalupdated Dec 2015 | Jan 2015 | granted May 2015 | Dec 2015 | Cornwall | 6.5 |
| Summercourt Solar Farm (Glebe Farm)solar farm | solar farm | 1.1 | operationalupdated Jun 2013 | Jun 2012 | granted Oct 2012 | Jun 2013 | Cornwall | 6.6 |
| St Columb Majorbattery storage | battery storage | 5 | approved, not builtupdated Jun 2025 | Apr 2025 | granted May 2025 | Jun 2025 | Cornwall | 6.9 |
| Trefullock Solar Farmsolar farm | solar farm | 5 | operationalupdated Sep 2015 | Oct 2010 | granted Jan 2011 | Sep 2015 | Cornwall | 7.1 |
| Trekenning Farm Battery Storage Facility & Co-Opbattery storage | battery storage | 5 | approved, not builtupdated May 2026 | Nov 2022 | granted Dec 2025 | May 2026 | Cornwall | 7.3 |
| Hendra Barns Solar Farmsolar farm | solar farm | 15 | permission expiredupdated Mar 2018 | Mar 2013 | granted Jul 2013 | Mar 2018 | Cornwall | 7.3 |
| Fair Park Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Nov 2025 | Apr 2023 | granted Oct 2025 | Nov 2025 | Cornwall | 7.5 |
| Fair Park Solar Farmbattery storage | battery storage | 20 | approved, not builtupdated Nov 2025 | Apr 2023 | granted Oct 2025 | Nov 2025 | Cornwall | 7.5 |
| Burthy Row Farm, Trefullock Moor Solar Farm & Battery Storagesolar farm | solar farm | 49.9 | application submitted may be out of dateupdated Apr 2023 | Mar 2023 | — | Apr 2023 | Cornwall | 8.0 |
| Burthy Farmsolar farm | solar farm | 10 | operationalupdated May 2015 | Jul 2013 | granted Sep 2014 | May 2015 | Cornwall | 8.1 |
| Goonabarn Farm Wind Turbineswind farm | wind farm | 1 | operationalupdated Apr 2016 | Feb 2013 | granted Jul 2013 | Apr 2016 | Cornwall | 8.1 |
| St Columb Major Solar Farmsolar farm | solar farm | 7 | operationalupdated May 2014 | Jan 2011 | granted Apr 2011 | May 2014 | Cornwall | 8.3 |
| Land At Pines Tipwind farm | wind farm | 2.7 | refused on appealupdated Oct 2017 | Feb 2015 | refused Mar 2016 | Oct 2017 | Cornwall | 8.4 |
| Truthan Barton Wind Farmwind farm | wind farm | 12.5 | refused on appealupdated Sep 2012 | May 2011 | refused Sep 2011 | Sep 2012 | Cornwall | 8.9 |
| Land near Ventonteaguewind turbine | wind turbine | 2.3 | operationalupdated Dec 2019 | Oct 2018 | granted Dec 2019 | Dec 2019 | Cornwall | 9.0 |
| Denzell Downs Wind Farmwind farm | wind farm | 10 | operationalupdated Jan 2016 | Jun 2013 | granted Dec 2013 | Jan 2016 | Cornwall | 9.1 |
| Trendeal Solar Farmsolar farm | solar farm | 12 | abandonedupdated Sep 2017 | Aug 2013 | granted Oct 2013 | Sep 2017 | Cornwall | 9.1 |
| Bears Down Wind Farmwind farm | wind farm | 9.8 | operationalupdated Dec 2003 | May 2000 | granted Jun 2000 | Dec 2003 | Cornwall | 9.7 |
| Indian Queens National Grid Substation, Domelick Hillbattery storage | battery storage | 50 | approved, not builtupdated May 2024 | Aug 2023 | granted Apr 2024 | May 2024 | Cornwall | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (5)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Treloggan Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Mar 2022 | Feb 2022 | granted Apr 2022 | Mar 2022 | Cornwall | 1.5 |
| Headland Hotel, Headland Roadsolar farm | solar farm | 0.2 | refusedupdated Aug 2023 | Jan 2023 | refused Aug 2023 | Aug 2023 | Cornwall | 4.5 |
| Trevornick Holiday Park, Holywell Baysolar farm | solar farm | 0.2 | approved, not built may be out of dateupdated May 2023 | Apr 2023 | granted May 2023 | May 2023 | Cornwall | 6.6 |
| Burthy Row Farm, Trefullock Moor Solar Farm & Battery Storagebattery storage | battery storage | — | application submitted may be out of dateupdated Apr 2023 | Mar 2023 | — | Apr 2023 | Cornwall | 8.0 |
| Perransands Holiday Centre, Perransands Holiday Park Solar PV Equipmentrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Apr 2023 | Dec 2022 | granted Feb 2023 | Apr 2023 | Cornwall | 8.8 |
Distance from the average position of the TR8 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 17 | 1 | 4 | 9 | 1 | 178 |
| Rooftop solar | 2 | 0 | 2 | 0 | 0 | 0.9 |
| Wind farm | 7 | 0 | 0 | 4 | 2 | 0 |
| Wind turbine | 2 | 0 | 0 | 1 | 1 | 0 |
| Battery storage | 7 | 1 | 6 | 0 | 0 | 128 |
MW in pipeline: pending, approved and under-construction capacity.
How Cornwall decides solar, wind and battery applications
| Applications | Cornwall | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 225 | 10,236 |
| Refused | 49 (22%) | 19% |
| Solar refused | 31 of 159 | 12% |
| Onshore wind refused | 15 of 39 | 45% |
| Battery storage refused | 3 of 27 | 16% |
| Median time from submission to decision | 16.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 23 / 20 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TR8, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.