Kernow Solar Farm (5 MW)

Kernow Solar Farm is a 5 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 November 2012; the record was last updated on 3 September 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
3 September 2018record last updated
Cornwallcouncil area

Planning timeline

DateStage
27 January 2011Application submitted
18 April 2011Planning permission granted
6 September 2012Construction started
30 November 2012Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
3 September 2018
Operator or applicant
Cornwall Council Property Services
Planning authority
Cornwall
Planning application reference
PA11/00498
Site area
14.5 ha
Address (REPD)
Trebarber, St. Mawgan Nr Newquay
Council area (by location)
Cornwall
Time to decision
12 weeks
REPD reference
1554

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
St Columb Majorbattery storage5approved, not built3.7
Trekenning Farm Battery Storage Facility & Co-Opbattery storage5approved, not built4.0
Tregonning Farm Solar Farm & Battery Storagesolar farm68under construction4.6
Denzell Downs Wind Farmwind farm10operational5.1
St Columb Major Solar Farmsolar farm7operational5.6
Bears Down Wind Farmwind farm9.8operational5.7
Bears Down Wind Farmwind farm22.5application submitted7.4
Burthy Row Farm, Trefullock Moor Solar Farm & Battery Storagesolar farm49.9application submitted7.8
Trefullock Solar Farmsolar farm5operational7.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.4298, -5.0054).