St Columb Major Solar Farm (7 MW)

St Columb Major Solar Farm is a 7 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 14 March 2014; the record was last updated on 22 May 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWsolar farm
operationalstatus in REPD
22 May 2014record last updated
Cornwallcouncil area

Planning timeline

DateStage
27 January 2011Application submitted
28 April 2011Planning permission granted
14 March 2014Operational

Project details

Technology
solar farm
Capacity
7 MW
Status (REPD)
operational
Record last updated
22 May 2014
Operator or applicant
Inazin Solar (previoulsy owned by Low Carbon Solar)
Planning authority
Cornwall
Planning application reference
PA11/00560
Site area
16.1 ha
Address (REPD)
Trekenning Farm, Trekenningm, Newquay, Cornwall
Council area (by location)
Cornwall
Time to decision
13 weeks
REPD reference
1566

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Trekenning Farm Battery Storage Facility & Co-Opbattery storage5approved, not built1.7
St Columb Majorbattery storage5approved, not built1.9
Indian Queens National Grid Substation, Domelick Hillbattery storage50approved, not built3.5
Indian Queens Sub station, Carne Hillbattery storage50approved, not built3.8
Indian Queens Sub-Stationbattery storage47.5approved, not built4.3
Burthy Row Farm, Trefullock Moor Solar Farm & Battery Storagesolar farm49.9application submitted5.3
Denzell Downs Wind Farmwind farm10operational5.3
Kernow Solar Farmsolar farm5operational5.6
Bears Down Wind Farmwind farm9.8operational5.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.4229, -4.9278).