Indian Queens National Grid Substation, Domelick Hill (50 MW battery storage)

Indian Queens National Grid Substation, Domelick Hill is a 50 MW battery storage project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 23 April 2024, not yet built; the record was last updated on 16 May 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
approved, not builtstatus in REPD
16 May 2024record last updated
Cornwallcouncil area

Planning timeline

DateStage
8 August 2023Application submitted
23 April 2024Planning permission granted
23 April 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
16 May 2024
Operator or applicant
EDF Energy Renewables (merged with Pivot Power)
Planning authority
Cornwall
Planning application reference
PA23/06527
Address (REPD)
Indian Queens National Grid Substation Domelick Hill, B3279 St Dennis
Council area (by location)
Cornwall
Time to decision
37 weeks
Name in REPD
Indian Queens National Grid Substation, Domelick Hill - Battery Storage
REPD reference
14687

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Indian Queens Sub station, Carne Hillbattery storage50approved, not built0.3
Indian Queens Sub-Stationbattery storage47.5approved, not built0.8
Burthy Row Farm, Trefullock Moor Solar Farm & Battery Storagesolar farm49.9application submitted3.5
St Columb Major Solar Farmsolar farm7operational3.5
Land at Gilley's Mill Damsolar farm5operational3.9
Kernick Mica Dam Solar Farmsolar farm12operational4.8
Trekenning Farm Battery Storage Facility & Co-Opbattery storage5approved, not built5.1
Burthy Farmsolar farm10operational5.1
Trefullock Solar Farmsolar farm5operational5.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.3968, -4.9003).