Energy Projects Near You

Indian Queens Sub-Station (47.5 MW battery storage)

Indian Queens Sub-Station is a 47.5 MW battery storage project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 October 2022, not yet built; the record was last updated on 25 July 2022. REPD also records that the planning permission expired on 17 October 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

47.5 MWbattery storage
approved, not builtmay be out of datestatus in REPD
25 July 2022record last updated
Cornwallcouncil area

REPD also records that the planning permission expired on 17 October 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
28 June 2022Application submitted
17 October 2022Planning permission granted
17 October 2025Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
47.5 MW
Status (REPD)
approved, not built
Record last updated
25 July 2022
Operator or applicant
Prime Energy Development Limited / Valero Energy / Sambar Power
Planning authority
Cornwall
Planning application reference
PA22/05961
Address (REPD)
South West Of Indian Queens Sub-station St Dennis
Council area (by location)
Cornwall
Time to decision
16 weeks
Name in REPD
Indian Queens Sub-Station - Battery Storage
REPD reference
11725

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Indian Queens Sub station, Carne Hillbattery storage50approved, not built0.5
Indian Queens National Grid Substation, Domelick Hillbattery storage50approved, not built0.8
Burthy Row Farm, Trefullock Moor Solar Farm & Battery Storagesolar farm49.9application submitted3.4
Land at Gilley's Mill Damsolar farm5operational3.5
Kernick Mica Dam Solar Farmsolar farm12operational4.2
St Columb Major Solar Farmsolar farm7operational4.3
Carloggas Farm Solar Parksolar farm8.3operational4.6
Scarcewater Tipwind farm6.9refused on appeal4.7
Burthy Farmsolar farm10operational4.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.3909, -4.895).