Kerriers Solar Park (9.6 MW)

Kerriers Solar Park is a 9.6 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 19 September 2014; the record was last updated on 29 September 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.6 MWsolar farm
operationalstatus in REPD
29 September 2015record last updated
Cornwallcouncil area

Planning timeline

DateStage
15 January 2013Application submitted
15 March 2013Planning permission granted
1 February 2014Construction started
19 September 2014Operational

Project details

Technology
solar farm
Capacity
9.6 MW
Status (REPD)
operational
Record last updated
29 September 2015
Operator or applicant
Kronos Solar
Planning authority
Cornwall
Planning application reference
PA12/10939
Address (REPD)
Land At Kerriers Withiel Bodmin Cornwall
Council area (by location)
Cornwall
Time to decision
8 weeks
REPD reference
2383

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bodwen Solar Parksolar farm5.5operational4.4
Tredinnick Fieldssolar farm5.8operational5.7
Land at Gilley's Mill Damsolar farm5operational5.7
St. Breock Re-Powerwind farm10operational5.9
Scotland Corner wind farmwind farm15refused6.8
Lower Bodiniel Farmsolar farm5operational6.9
Middle Treworder Farmsolar farm5operational7.1
Bodmin 2 Solar Farmsolar farm5.3operational7.4
Indian Queens National Grid Substation, Domelick Hillbattery storage50approved, not built7.8