Kerriers Solar Park (9.6 MW)
Kerriers Solar Park is a 9.6 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 19 September 2014; the record was last updated on 29 September 2015.
9.6 MWsolar farm
operationalstatus in REPD
29 September 2015record last updated
Cornwallcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 15 January 2013 | Application submitted |
| 15 March 2013 | Planning permission granted |
| 1 February 2014 | Construction started |
| 19 September 2014 | Operational |
Project details
- Technology
- solar farm
- Capacity
- 9.6 MW
- Status (REPD)
- operational
- Record last updated
- 29 September 2015
- Operator or applicant
- Kronos Solar
- Planning authority
- Cornwall
- Planning application reference
- PA12/10939
- Address (REPD)
- Land At Kerriers Withiel Bodmin Cornwall
- Council area (by location)
- Cornwall
- Time to decision
- 8 weeks
- REPD reference
- 2383
Who decides
| Applications | Cornwall | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 225 | 10,236 |
| Refused | 49 (22%) | 19% |
| Solar refused | 31 of 159 | 12% |
| Onshore wind refused | 15 of 39 | 45% |
| Battery storage refused | 3 of 27 | 16% |
| Median time from submission to decision | 16.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 23 / 20 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Bodwen Solar Park | solar farm | 5.5 | operational | 4.4 |
| Tredinnick Fields | solar farm | 5.8 | operational | 5.7 |
| Land at Gilley's Mill Dam | solar farm | 5 | operational | 5.7 |
| St. Breock Re-Power | wind farm | 10 | operational | 5.9 |
| Scotland Corner wind farm | wind farm | 15 | refused | 6.8 |
| Lower Bodiniel Farm | solar farm | 5 | operational | 6.9 |
| Middle Treworder Farm | solar farm | 5 | operational | 7.1 |
| Bodmin 2 Solar Farm | solar farm | 5.3 | operational | 7.4 |
| Indian Queens National Grid Substation, Domelick Hill | battery storage | 50 | approved, not built | 7.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.4424, -4.8164).