Energy Projects Near You

Treswarrow Solar Park (6.5 MW)

Treswarrow Solar Park is a 6.5 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 18 March 2015; the record was last updated on 31 March 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.5 MWsolar farm
operationalstatus in REPD
31 March 2015record last updated
Cornwallcouncil area

Planning timeline

DateStage
16 May 2013Application submitted
25 October 2013Refused by the planning authority
11 February 2014Appeal lodged
20 October 2014Planning permission granted
20 October 2014Appeal allowed
2 January 2015Construction started
18 March 2015Operational

Project details

Technology
solar farm
Capacity
6.5 MW
Status (REPD)
operational
Record last updated
31 March 2015
Operator or applicant
Private Developer
Planning authority
Cornwall
Planning application reference
PA13/04287
Appeal reference
APP/D0840/A/14/2213107
Site area
15.0 ha
Address (REPD)
Treswarrow, Trelights, Port Isaac, Cornwall
Council area (by location)
Cornwall
Time to decision
75 weeks
REPD reference
1641

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Middle Treworder Farmsolar farm5operational7.2
St. Breock Re-Powerwind farm10operational8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.5679, -4.8498).