Land At Woodlands Farm (8 MW solar farm)
Land At Woodlands Farm is an 8 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 2 January 2014; the record was last updated on 30 September 2015.
8 MWsolar farm
refusedstatus in REPD
30 September 2015record last updated
Cornwallcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 25 January 2013 | Application submitted |
| 2 January 2014 | Refused by the planning authority |
Project details
- Technology
- solar farm
- Capacity
- 8 MW
- Status (REPD)
- refused
- Record last updated
- 30 September 2015
- Operator or applicant
- Kronos Solar
- Planning authority
- Cornwall
- Planning application reference
- PA12/12014
- Address (REPD)
- North Tamerton Holsworthy
- Council area (by location)
- Cornwall
- Time to decision
- 49 weeks
- REPD reference
- 1738
Who decides
| Applications | Cornwall | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 225 | 10,236 |
| Refused | 49 (22%) | 19% |
| Solar refused | 31 of 159 | 12% |
| Onshore wind refused | 15 of 39 | 45% |
| Battery storage refused | 3 of 27 | 16% |
| Median time from submission to decision | 16.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 23 / 20 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Pinkworthy Farm, Pyworthy | battery storage | 25 | approved, not built | 1.9 |
| CRINACOTT SOLAR FARM (Pyworthy) | solar farm | 6.7 | operational | 2.0 |
| Solar Farm at Land At Monks Farm And Trelana Pyworthy Holsworthy | solar farm | 42 | operational | 2.2 |
| Stoneworthy | battery storage | 49.9 | approved, not built | 2.5 |
| Bradford Solar Park | solar farm | 5.3 | operational | 2.5 |
| Land At Southland Farm (NOR) | solar farm | 5 | abandoned | 3.0 |
| Northmoor | solar farm | 5 | operational | 3.9 |
| Derriton Fields Solar Farm | solar farm | 11.8 | operational | 4.3 |
| Hornacott Solar Park | solar farm | 5 | refused on appeal | 5.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.773, -4.408).