Energy Projects Near You

Solar, wind and battery projects near Holsworthy (EX22)

23 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EX22 (Torridge): 1 is waiting for a planning decision, 4 approved but not yet running, 13 operational. The largest live scheme is Stoneworthy (49.9 MW battery storage, approved on 3 July 2025, not yet built), 4.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

23projects within 10 km
1awaiting a decision
4approved, not running
13operational

Projects within 10 km of EX22

Projects of 1 MW and more (21)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Great Knowle Farm Solarsolar farmsolar farm3operationalupdated Feb 2013Apr 2011granted Jun 2011Feb 2013Torridge2.7
Derriton Fields Solar Farmsolar farmsolar farm11.8operationalupdated Apr 2014Nov 2012granted Feb 2013Apr 2014Torridge2.8
Cairn Brae Wind Turbinewind farmwind farm1.3application withdrawnupdated Dec 2004——Dec 2004Torridge3.8
Pitworthy Farm Solar Parksolar farmsolar farm15.6operationalupdated Mar 2018Oct 2012granted Jul 2013Mar 2018Torridge4.2
Stoneworthybattery storagebattery storage49.9approved, not builtupdated Jul 2025Jun 2024granted Jul 2025Jul 2025Torridge4.3
Land West of Parsonage Woodsolar farmsolar farm4.2operationalupdated May 2017Aug 2015granted Sep 2015May 2017Torridge4.8
CRINACOTT SOLAR FARM (Pyworthy)solar farmsolar farm6.7operationalupdated Feb 2016Oct 2012granted Jan 2013Feb 2016Torridge4.8
Solar Farm at Land At Monks Farm And Trelana Pyworthy Holsworthysolar farmsolar farm42operationalupdated Nov 2025Jan 2021granted Nov 2021Nov 2025Torridge5.5
Land At Southland Farm (NOR)solar farmsolar farm5abandonedupdated Mar 2019Aug 2015granted Apr 2016Mar 2019Torridge5.9
Foxcombe Farm Solar Parksolar farmsolar farm5operationalupdated Nov 2013Sep 2012granted Feb 2013Nov 2013Torridge6.0
East Langford Farmsolar farmsolar farm5operationalupdated Sep 2011Feb 2011granted Apr 2011Sep 2011Cornwall6.2
Eastacombe Solar Farmsolar farmsolar farm3.6operationalupdated Oct 2012Apr 2011granted Jun 2011Oct 2012Torridge6.6
Land At Woodlands Farmsolar farmsolar farm8refusedupdated Sep 2015Jan 2013refused Jan 2014Sep 2015Cornwall6.7
Pinkworthy Farm, Pyworthybattery storagebattery storage25approved, not builtupdated Sep 2024Mar 2024granted Sep 2024Sep 2024Torridge7.0
Bradford Solar Parksolar farmsolar farm5.3operationalupdated Apr 2013Jun 2011granted Dec 2011Apr 2013Torridge7.4
Dunsland Cross Wind Farmwind farmwind farm7.5operationalupdated Oct 2017Jan 2012granted Jan 2013Oct 2017Torridge7.9
Wheelers Crosswind farmwind farm7.8refusedupdated Jan 2013Apr 2011refused Dec 2012Jan 2013Torridge8.0
Hunscott Solar Farmsolar farmsolar farm1application withdrawnupdated Aug 2017Mar 2012—Aug 2017Torridge8.6
East Rightadown Farm, Brandis Corner Solar Farmsolar farmsolar farm7.6approved, not builtupdated Jul 2025Feb 2023granted Sep 2023Jul 2025Torridge9.1
West Venn Solar Farmsolar farmsolar farm5operationalupdated May 2017Jun 2015granted Oct 2015May 2017Torridge9.5
Nethercott Farmwind farmwind farm1.5operationalupdated May 2018Jan 2014granted Jul 2014May 2018Torridge9.6
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Tatson Farmwind turbinewind turbine—application submittedupdated Apr 2025Mar 2025—Apr 2025Torridge6.2
East Rightadown Farm, Brandis Cornerbattery storagebattery storage—approved, not builtupdated Jul 2025Feb 2023granted Sep 2023Jul 2025Torridge9.1

Distance from the average position of the EX22 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm15011117.6
Wind farm400210
Wind turbine110000
Battery storage3030074.9

MW in pipeline: pending, approved and under-construction capacity.

How Torridge decides solar, wind and battery applications

ApplicationsTorridgeUK
Decided applications (solar, wind, battery)4510,236
Refused12 (27%)19%
Solar refused4 of 3112%
Onshore wind refused6 of 845%
Battery storage refused2 of 616%
Median time from submission to decision24.1 weeks17.0 weeks
Appeals lodged / allowed3 / 7—

All projects in Torridge

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.