Solar, wind and battery projects near Bude (EX23)
14 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EX23 (Cornwall): 1 is waiting for a planning decision, 3 approved but not yet running, 7 operational. The largest live scheme is Pinkworthy Farm, Pyworthy (25 MW battery storage, approved on 5 September 2024, not yet built), 8.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of EX23
Projects of 1 MW and more (12)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Whalesborough Farm, Marhamchurchsolar farm | solar farm | 2.1 | approved, not builtupdated Feb 2024 | Jul 2023 | granted Feb 2024 | Feb 2024 | Cornwall | 2.0 |
| Creathorne Farm Solar Farmsolar farm | solar farm | 1.8 | operationalupdated Aug 2017 | Jan 2013 | granted Sep 2013 | Aug 2017 | Cornwall | 3.3 |
| Creathorne Farm Solar Farm - extensionsolar farm | solar farm | 2.2 | application withdrawnupdated Jun 2014 | Mar 2014 | — | Jun 2014 | Cornwall | 3.4 |
| Pitworthy Farm Solar Parksolar farm | solar farm | 15.6 | operationalupdated Mar 2018 | Oct 2012 | granted Jul 2013 | Mar 2018 | Torridge | 7.4 |
| Land At Southland Farm (NOR)solar farm | solar farm | 5 | abandonedupdated Mar 2019 | Aug 2015 | granted Apr 2016 | Mar 2019 | Torridge | 7.7 |
| Bradford Solar Parksolar farm | solar farm | 5.3 | operationalupdated Apr 2013 | Jun 2011 | granted Dec 2011 | Apr 2013 | Torridge | 8.0 |
| Pinkworthy Farm, Pyworthybattery storage | battery storage | 25 | approved, not builtupdated Sep 2024 | Mar 2024 | granted Sep 2024 | Sep 2024 | Torridge | 8.5 |
| Solar Farm at Land At Monks Farm And Trelana Pyworthy Holsworthysolar farm | solar farm | 42 | operationalupdated Nov 2025 | Jan 2021 | granted Nov 2021 | Nov 2025 | Torridge | 8.7 |
| East Langford Farmsolar farm | solar farm | 5 | operationalupdated Sep 2011 | Feb 2011 | granted Apr 2011 | Sep 2011 | Cornwall | 9.0 |
| CRINACOTT SOLAR FARM (Pyworthy)solar farm | solar farm | 6.7 | operationalupdated Feb 2016 | Oct 2012 | granted Jan 2013 | Feb 2016 | Torridge | 9.9 |
| Northmoorsolar farm | solar farm | 5 | operationalupdated May 2016 | Sep 2014 | granted Nov 2014 | May 2016 | Cornwall | 10.0 |
| Big Field Wind Farmwind farm | wind farm | 25.3 | refused on appealupdated Oct 2018 | Mar 2014 | refused Oct 2014 | Oct 2018 | Cornwall | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (2)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Morrisons, Stucley Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Dec 2022 | Oct 2022 | granted Dec 2022 | Dec 2022 | Cornwall | 0.5 |
| Tatson Farmwind turbine | wind turbine | — | application submittedupdated Apr 2025 | Mar 2025 | — | Apr 2025 | Torridge | 7.6 |
Distance from the average position of the EX23 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 10 | 0 | 1 | 7 | 0 | 2.1 |
| Rooftop solar | 1 | 0 | 1 | 0 | 0 | 0.3 |
| Wind farm | 1 | 0 | 0 | 0 | 1 | 0 |
| Wind turbine | 1 | 1 | 0 | 0 | 0 | 0 |
| Battery storage | 1 | 0 | 1 | 0 | 0 | 25 |
MW in pipeline: pending, approved and under-construction capacity.
How Cornwall decides solar, wind and battery applications
| Applications | Cornwall | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 225 | 10,236 |
| Refused | 49 (22%) | 19% |
| Solar refused | 31 of 159 | 12% |
| Onshore wind refused | 15 of 39 | 45% |
| Battery storage refused | 3 of 27 | 16% |
| Median time from submission to decision | 16.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 23 / 20 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.