Big Field Wind Farm (25.3 MW)

Big Field Wind Farm is a 25.3 MW wind farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 26 July 2017; the record was last updated on 24 October 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25.3 MWwind farm
refused on appealstatus in REPD
24 October 2018record last updated
Cornwallcouncil area

Planning timeline

DateStage
6 March 2014Application submitted
28 October 2014Refused by the planning authority
16 June 2015Appeal lodged
26 July 2017Appeal refused

Project details

Technology
wind farm
Capacity
25.3 MW
Status (REPD)
refused on appeal
Record last updated
24 October 2018
Operator or applicant
Good Energy
Planning authority
Cornwall
Planning application reference
PA14/02107
Appeal reference
APP/D0840/W/15/3014917
Turbines
11
Address (REPD)
The Big Field Wind Farm Land At And Adjoining Creddacott Farm, Week St Mary, Holsworthy
Council area (by location)
Cornwall
Time to decision
34 weeks
REPD reference
4545

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Higher Witheven Solarsolar farm42.5approved, not built3.7
Canworthy Watersolar farm41operational3.8
Northmoorsolar farm5operational3.9
Villaton Farm Solar Parksolar farm12.5refused5.6
Winsdon Farmsolar farm5operational5.7
Grange Farm (Cornwall)solar farm5operational6.2
Hornacott Solar Parksolar farm5refused on appeal6.4
Bradford Solar Parksolar farm5.3operational6.5
Pinkworthy Farm, Pyworthybattery storage25approved, not built6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7367, -4.5015).