Higher Witheven Solar (42.5 MW)

Higher Witheven Solar is a 42.5 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 19 August 2025, not yet built; the record was last updated on 8 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

42.5 MWsolar farm
approved, not builtstatus in REPD
8 June 2026record last updated
Cornwallcouncil area

Planning timeline

DateStage
21 June 2023Application submitted
21 August 2024Refused by the planning authority
20 December 2024Appeal lodged
19 August 2025Planning permission granted
19 August 2025Appeal allowed
19 August 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
42.5 MW
Status (REPD)
approved, not built
Record last updated
8 June 2026
Operator or applicant
Downing Renewables
Planning authority
Cornwall
Planning application reference
PA23/04306
Appeal reference
APP/D0840/W/24/3358031
Site area
82.1 ha
Address (REPD)
N/O Canworthy House Canworthy Water Launceston
Council area (by location)
Cornwall
Time to decision
113 weeks
Contracts for Difference
AR7a
REPD reference
10483

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Canworthy Watersolar farm41operational1.4
Big Field Wind Farmwind farm25.3refused on appeal3.7
Winsdon Farmsolar farm5operational4.3
Grange Farm (Cornwall)solar farm5operational6.2
Villaton Farm Solar Parksolar farm12.5refused6.5
Northmoorsolar farm5operational6.7
Cold Northcottwind farm6.6operational7.0
Hornacott Solar Parksolar farm5refused on appeal7.3
Lower Tregeen Farmsolar farm5approved, not built7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7039, -4.51).