Energy Projects Near You

Lower Tregeen Farm (5 MW solar farm)

Lower Tregeen Farm is a 5 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 15 April 2016, not yet built; the record was last updated on 30 October 2018. REPD also records that the planning permission expired on 15 April 2019, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
approved, not builtmay be out of datestatus in REPD
30 October 2018record last updated
Cornwallcouncil area

REPD also records that the planning permission expired on 15 April 2019, so the project may not go ahead in this form.

Planning timeline

DateStage
16 December 2015Application submitted
15 April 2016Planning permission granted
15 April 2019Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
approved, not built
Record last updated
30 October 2018
Operator or applicant
Powerquinn
Planning authority
Cornwall
Planning application reference
PA15/11004
Site area
8.9 ha
Address (REPD)
Land At Lower Tregeen Farm, Davidstow, Camelford
Council area (by location)
Cornwall
Time to decision
17 weeks
REPD reference
5954

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hendraburnickwind farm8application withdrawn4.1
Cold Northcottwind farm6.6operational4.5
Davidstow Wind Farmwind farm48application withdrawn4.6
Bodmin Moorwind farm50appeal withdrawn5.1
Worthy Vale Manorwind farm10.1refused5.6
Higher Witheven Solarsolar farm42.5approved, not built7.4
Delabole (Repowering)wind farm9.2operational8.3
Canworthy Watersolar farm41operational8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.6684, -4.5987).