Bodmin Moor (50 MW wind farm)

Bodmin Moor is a 50 MW wind farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: appeal withdrawn; the record was last updated on 9 December 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWwind farm
appeal withdrawnstatus in REPD
9 December 2015record last updated
Cornwallcouncil area

Planning timeline

DateStage
18 July 2008Application submitted
26 July 2010Refused by the planning authority
11 March 2011Appeal lodged
27 September 2011Appeal withdrawn

Project details

Technology
wind farm
Capacity
50 MW
Status (REPD)
appeal withdrawn
Record last updated
9 December 2015
Operator or applicant
Community Power Ltd
Planning authority
Cornwall
Planning application reference
E1/2008/01432
Appeal reference
11/00031/REF
Turbines
20
Address (REPD)
Davidstow , Cornwall
Council area (by location)
Cornwall
Time to decision
105 weeks
REPD reference
3027

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Davidstow Wind Farmwind farm48application withdrawn0.5
Hendraburnickwind farm8application withdrawn3.7
Worthy Vale Manorwind farm10.1refused4.5
Lower Tregeen Farmsolar farm5approved, not built5.1
Delabole (Repowering)wind farm9.2operational5.4
Cold Northcottwind farm6.6operational6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.6275, -4.6301).