Worthy Vale Manor (10.1 MW wind farm)

Worthy Vale Manor is a 10.1 MW wind farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 28 June 1996; the record was last updated on 16 February 2005.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.1 MWwind farm
refusedstatus in REPD
16 February 2005record last updated
Cornwallcouncil area

Planning timeline

DateStage
8 November 1993Application submitted
28 June 1996Refused by the planning authority

Project details

Technology
wind farm
Capacity
10.1 MW
Status (REPD)
refused
Record last updated
16 February 2005
Operator or applicant
Worthyvale Manor Partnership
Planning authority
Cornwall
Planning application reference
not recorded
Address (REPD)
Worthyvale Manor Camelford Cornwall
Council area (by location)
Cornwall
Time to decision
138 weeks
REPD reference
2648

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hendraburnickwind farm8application withdrawn1.5
Delabole (Repowering)wind farm9.2operational3.0
Bodmin Moorwind farm50appeal withdrawn4.5
Davidstow Wind Farmwind farm48application withdrawn4.6
Lower Tregeen Farmsolar farm5approved, not built5.6
Cold Northcottwind farm6.6operational9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.6564, -4.6753).