Energy Projects Near You

Solar, wind and battery projects near Tintagel (PL34)

13 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PL34 (Cornwall): 1 is waiting for a planning decision, 1 approved but not yet running, 4 operational. The largest live scheme is Helsbury Park Woods, Michaelstow (0.9 MW wind turbine, application submitted on 12 September 2024, no decision recorded), 8.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13projects within 10 km
1awaiting a decision
1approved, not running
4operational

Projects within 10 km of PL34

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Delabole (Repowering)wind farmwind farm9.2operationalupdated Feb 2011Apr 2008granted Dec 2009Feb 2011Cornwall3.7
Delabole Wind Farmwind farmwind farm4decommissionedupdated Jan 2015Apr 2008—Jan 2015Cornwall3.8
Delabolesolar farmsolar farm2permission expiredupdated Jul 2020Sep 2015granted Feb 2016Jul 2020Cornwall4.7
Worthy Vale Manorwind farmwind farm10.1refusedupdated Feb 2005Nov 1993refused Jun 1996Feb 2005Cornwall4.9
Hendraburnickwind farmwind farm8application withdrawnupdated Apr 2011Jun 2007—Apr 2011Cornwall6.4
Saputo Dairy UKsolar farmsolar farm4.2operationalupdated Mar 2022Apr 2020granted Apr 2022Mar 2022Cornwall7.7
Trehane Farmsolar farmsolar farm1.4application withdrawnupdated Aug 2017Mar 2012—Aug 2017Cornwall8.4
Bodmin Moorwind farmwind farm50appeal withdrawnupdated Dec 2015Jul 2008refused Jul 2010Dec 2015Cornwall8.8
Davidstow Wind Farmwind farmwind farm48application withdrawnupdated Jan 2014Aug 2013—Jan 2014Cornwall9.1
Otterham Down Wind Farmwind farmwind farm3.2operationalupdated Nov 2014Jun 2006granted Oct 2009Nov 2014Cornwall9.9
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Bowood Golf Club, Bowood Parkrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Aug 2024granted Sep 2025Jan 2026Cornwall6.3
Saputo Dairy UKbattery storagebattery storage—operationalupdated Mar 2022Apr 2020granted Jul 2020Mar 2022Cornwall7.7
Helsbury Park Woods, Michaelstowwind turbinewind turbine0.9application submittedupdated Sep 2024Sep 2024—Sep 2024Cornwall8.5

Distance from the average position of the PL34 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm300100
Rooftop solar101000.2
Wind farm700210
Wind turbine110000.9
Battery storage100100

MW in pipeline: pending, approved and under-construction capacity.

How Cornwall decides solar, wind and battery applications

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

All projects in Cornwall

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.