Hendraburnick (8 MW wind farm)
Hendraburnick is an 8 MW wind farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 7 July 2009; the record was last updated on 4 April 2011.
8 MWwind farm
application withdrawnstatus in REPD
4 April 2011record last updated
Cornwallcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 30 June 2007 | Application submitted |
| 7 July 2009 | Application withdrawn |
Project details
- Technology
- wind farm
- Capacity
- 8 MW
- Status (REPD)
- application withdrawn
- Record last updated
- 4 April 2011
- Operator or applicant
- Ecotricity
- Planning authority
- Cornwall
- Planning application reference
- 2007/01497
- Turbines
- 4
- Address (REPD)
- Hendraburnick Davidstow Cornwall
- Council area (by location)
- Cornwall
- REPD reference
- 3029
Who decides
| Applications | Cornwall | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 225 | 10,236 |
| Refused | 49 (22%) | 19% |
| Solar refused | 31 of 159 | 12% |
| Onshore wind refused | 15 of 39 | 45% |
| Battery storage refused | 3 of 27 | 16% |
| Median time from submission to decision | 16.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 23 / 20 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Worthy Vale Manor | wind farm | 10.1 | refused | 1.5 |
| Davidstow Wind Farm | wind farm | 48 | application withdrawn | 3.6 |
| Bodmin Moor | wind farm | 50 | appeal withdrawn | 3.7 |
| Lower Tregeen Farm | solar farm | 5 | approved, not built | 4.1 |
| Delabole (Repowering) | wind farm | 9.2 | operational | 4.2 |
| Cold Northcott | wind farm | 6.6 | operational | 7.7 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.6569, -4.6541).