Hendraburnick (8 MW wind farm)

Hendraburnick is an 8 MW wind farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 7 July 2009; the record was last updated on 4 April 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8 MWwind farm
application withdrawnstatus in REPD
4 April 2011record last updated
Cornwallcouncil area

Planning timeline

DateStage
30 June 2007Application submitted
7 July 2009Application withdrawn

Project details

Technology
wind farm
Capacity
8 MW
Status (REPD)
application withdrawn
Record last updated
4 April 2011
Operator or applicant
Ecotricity
Planning authority
Cornwall
Planning application reference
2007/01497
Turbines
4
Address (REPD)
Hendraburnick Davidstow Cornwall
Council area (by location)
Cornwall
REPD reference
3029

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Worthy Vale Manorwind farm10.1refused1.5
Davidstow Wind Farmwind farm48application withdrawn3.6
Bodmin Moorwind farm50appeal withdrawn3.7
Lower Tregeen Farmsolar farm5approved, not built4.1
Delabole (Repowering)wind farm9.2operational4.2
Cold Northcottwind farm6.6operational7.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.6569, -4.6541).