Energy Projects Near You

Solar, wind and battery projects near Boscastle (PL35)

15 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PL35 (Cornwall): 1 is waiting for a planning decision, 3 approved but not yet running, 4 operational. The largest live scheme is Lower Tregeen Farm (5 MW solar farm, approved on 15 April 2016, not yet built; REPD status may be out of date), 6.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15projects within 10 km
1awaiting a decision
3approved, not running
4operational

Projects within 10 km of PL35

Projects of 1 MW and more (11)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Worthy Vale Manorwind farmwind farm10.1refusedupdated Feb 2005Nov 1993refused Jun 1996Feb 2005Cornwall3.2
Hendraburnickwind farmwind farm8application withdrawnupdated Apr 2011Jun 2007—Apr 2011Cornwall3.8
Trehane Farmsolar farmsolar farm1.4application withdrawnupdated Aug 2017Mar 2012—Aug 2017Cornwall5.0
Otterham Down Wind Farmwind farmwind farm3.2operationalupdated Nov 2014Jun 2006granted Oct 2009Nov 2014Cornwall5.3
Delabole (Repowering)wind farmwind farm9.2operationalupdated Feb 2011Apr 2008granted Dec 2009Feb 2011Cornwall5.4
Saputo Dairy UKsolar farmsolar farm4.2operationalupdated Mar 2022Apr 2020granted Apr 2022Mar 2022Cornwall5.5
Delabole Wind Farmwind farmwind farm4decommissionedupdated Jan 2015Apr 2008—Jan 2015Cornwall5.8
Lower Tregeen Farmsolar farmsolar farm5approved, not built may be out of dateupdated Oct 2018Dec 2015granted Apr 2016Oct 2018Cornwall6.4
Delabolesolar farmsolar farm2permission expiredupdated Jul 2020Sep 2015granted Feb 2016Jul 2020Cornwall6.9
Davidstow Wind Farmwind farmwind farm48application withdrawnupdated Jan 2014Aug 2013—Jan 2014Cornwall7.4
Bodmin Moorwind farmwind farm50appeal withdrawnupdated Dec 2015Jul 2008refused Jul 2010Dec 2015Cornwall7.5
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Saputo Dairy UKbattery storagebattery storage—operationalupdated Mar 2022Apr 2020granted Jul 2020Mar 2022Cornwall5.5
Lower Tregeen, Davidstowwind turbinewind turbine0.9under constructionupdated Sep 2022Nov 2018granted Mar 2019Sep 2022Cornwall6.3
Bowood Golf Club, Bowood Parkrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Aug 2024granted Sep 2025Jan 2026Cornwall8.1
Tregida, Warbstowwind turbinewind turbine0.2application submittedApr 2026——Cornwall8.2

Distance from the average position of the PL35 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm401105
Rooftop solar101000.2
Wind farm700210
Wind turbine211001.1
Battery storage100100

MW in pipeline: pending, approved and under-construction capacity.

How Cornwall decides solar, wind and battery applications

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

All projects in Cornwall

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PL35, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.