Energy Projects Near You

Canworthy Water (41 MW solar farm)

Canworthy Water is a 41 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 10 December 2014; the record was last updated on 3 January 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

41 MWsolar farm
operationalstatus in REPD
3 January 2017record last updated
Cornwallcouncil area

Planning timeline

DateStage
22 August 2012Application submitted
21 January 2013Planning permission granted
28 February 2014Construction started
10 December 2014Operational

Project details

Technology
solar farm
Capacity
41 MW
Status (REPD)
operational
Record last updated
3 January 2017
Operator or applicant
Equitix
Planning authority
Cornwall
Planning application reference
PA12/07626
Site area
56.1 ha
Address (REPD)
Land west of South Wheatley, Wheatley Road, Nr Canworthy Water, Launceston
Council area (by location)
Cornwall
Time to decision
22 weeks
REPD reference
1630

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Higher Witheven Solarsolar farm42.5approved, not built1.4
Winsdon Farmsolar farm5operational3.0
Big Field Wind Farmwind farm25.3refused on appeal3.8
Grange Farm (Cornwall)solar farm5operational4.8
Villaton Farm Solar Parksolar farm12.5refused5.3
Northmoorsolar farm5operational6.0
Hornacott Solar Parksolar farm5refused on appeal6.1
Parabel North Beer Solar Farmsolar farm6.8operational6.2
West Ditchen Farmsolar farm5operational6.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7035, -4.4906).