Grange Farm (Cornwall) (5 MW solar farm)

Grange Farm (Cornwall) is a 5 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 28 February 2013; the record was last updated on 29 September 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
29 September 2015record last updated
Cornwallcouncil area

Planning timeline

DateStage
4 March 2011Application submitted
24 May 2011Planning permission granted
28 February 2013Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
29 September 2015
Operator or applicant
Vogt Solar
Planning authority
Cornwall
Planning application reference
PA11/01592
Site area
15.7 ha
Address (REPD)
Boyton, Launceston, Cornwall
Council area (by location)
Cornwall
Time to decision
12 weeks
REPD reference
1572

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Villaton Farm Solar Parksolar farm12.5refused1.7
Parabel North Beer Solar Farmsolar farm6.8operational1.8
Hornacott Solar Parksolar farm5refused on appeal1.9
West Ditchen Farmsolar farm5operational1.9
Winsdon Farmsolar farm5operational2.3
Canworthy Watersolar farm41operational4.8
Northmoorsolar farm5operational4.8
Higher Witheven Solarsolar farm42.5approved, not built6.2
Big Field Wind Farmwind farm25.3refused on appeal6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.711, -4.4233).