Hornacott Solar Park (5 MW)

Hornacott Solar Park is a 5 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 21 March 2016; the record was last updated on 4 April 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
refused on appealstatus in REPD
4 April 2016record last updated
Cornwallcouncil area

Planning timeline

DateStage
1 April 2015Application submitted
5 June 2015Refused by the planning authority
7 October 2015Appeal lodged
21 March 2016Appeal refused

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
refused on appeal
Record last updated
4 April 2016
Operator or applicant
Lightsource Renewable Energy
Planning authority
Cornwall
Planning application reference
PA15/03083
Appeal reference
APP/D0840/W/15/3134592
Site area
22.7 ha
Address (REPD)
Land At Hornacott, West Ditchin, North Tamerton, Launceston,
Council area (by location)
Cornwall
Time to decision
9 weeks
REPD reference
5170

Earlier applications for this site

ApplicationMWSubmittedOutcome
Hornacott Solar Park PA14/082702911 September 2014refused 19 December 2014

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
West Ditchen Farmsolar farm5operational0.6
Villaton Farm Solar Parksolar farm12.5refused0.8
Grange Farm (Cornwall)solar farm5operational1.9
Parabel North Beer Solar Farmsolar farm6.8operational2.9
Northmoorsolar farm5operational3.8
Winsdon Farmsolar farm5operational4.1
Land At Woodlands Farmsolar farm8refused5.2
Canworthy Watersolar farm41operational6.1
Pinkworthy Farm, Pyworthybattery storage25approved, not built6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7267, -4.4126).