Energy Projects Near You

Pinkworthy Farm, Pyworthy (25 MW battery storage)

Pinkworthy Farm, Pyworthy is a 25 MW battery storage project in Torridge, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 5 September 2024, not yet built; the record was last updated on 10 September 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWbattery storage
approved, not builtstatus in REPD
10 September 2024record last updated
Torridgecouncil area

Planning timeline

DateStage
7 March 2024Application submitted
5 September 2024Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
25 MW
Status (REPD)
approved, not built
Record last updated
10 September 2024
Operator or applicant
Private Developer
Planning authority
Torridge
Planning application reference
1/0127/2024/FUL
Address (REPD)
Pinkworthy Farm Pyworthy
Council area (by location)
Torridge
Time to decision
26 weeks
Name in REPD
Pinkworthy Farm, Pyworthy - Battery Storage
REPD reference
16068

Earlier applications for this site

ApplicationMWSubmittedOutcome
Pinkworthy Farm, Pyworthy 1/0146/2023/OUT5015 March 2023replaced by a revised application

Who decides

ApplicationsTorridgeUK
Decided applications (solar, wind, battery)4510,236
Refused12 (27%)19%
Solar refused4 of 3112%
Onshore wind refused6 of 845%
Battery storage refused2 of 616%
Median time from submission to decision24.1 weeks17.0 weeks
Appeals lodged / allowed3 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bradford Solar Parksolar farm5.3operational0.6
Solar Farm at Land At Monks Farm And Trelana Pyworthy Holsworthysolar farm42operational1.5
Land At Southland Farm (NOR)solar farm5abandoned1.6
Land At Woodlands Farmsolar farm8refused1.9
CRINACOTT SOLAR FARM (Pyworthy)solar farm6.7operational2.5
Stoneworthybattery storage49.9approved, not built2.9
Northmoorsolar farm5operational3.5
Pitworthy Farm Solar Parksolar farm15.6operational4.6
Derriton Fields Solar Farmsolar farm11.8operational5.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7802, -4.433).