Energy Projects Near You

Stoneworthy (49.9 MW battery storage)

Stoneworthy is a 49.9 MW battery storage project in Torridge, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 3 July 2025, not yet built; the record was last updated on 25 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtstatus in REPD
25 July 2025record last updated
Torridgecouncil area

Planning timeline

DateStage
3 June 2024Application submitted
20 September 2024Refused by the planning authority
23 December 2024Appeal lodged
3 July 2025Planning permission granted
3 July 2025Appeal allowed
3 July 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
25 July 2025
Operator or applicant
RES Limited
Planning authority
Torridge
Planning application reference
1/0514/2024/FULM
Appeal reference
APP/W1145/W/24/3358116
Address (REPD)
Near Lower Hopworthy, Pyworthy
Council area (by location)
Torridge
Time to decision
56 weeks
Name in REPD
Stoneworthy - Battery Energy Storage System
REPD reference
16561

Who decides

ApplicationsTorridgeUK
Decided applications (solar, wind, battery)4510,236
Refused12 (27%)19%
Solar refused4 of 3112%
Onshore wind refused6 of 845%
Battery storage refused2 of 616%
Median time from submission to decision24.1 weeks17.0 weeks
Appeals lodged / allowed3 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
CRINACOTT SOLAR FARM (Pyworthy)solar farm6.7operational0.5
Solar Farm at Land At Monks Farm And Trelana Pyworthy Holsworthysolar farm42operational1.6
Derriton Fields Solar Farmsolar farm11.8operational2.3
Land At Woodlands Farmsolar farm8refused2.5
Land At Southland Farm (NOR)solar farm5abandoned2.5
Pinkworthy Farm, Pyworthybattery storage25approved, not built2.9
Bradford Solar Parksolar farm5.3operational3.4
Pitworthy Farm Solar Parksolar farm15.6operational3.7
Northmoorsolar farm5operational6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7943, -4.398).