Pitworthy Farm Solar Park (15.6 MW)
Pitworthy Farm Solar Park is a 15.6 MW solar farm project in Torridge, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2014; the record was last updated on 2 March 2018.
15.6 MWsolar farm
operationalstatus in REPD
2 March 2018record last updated
Torridgecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 18 October 2012 | Application submitted |
| 4 July 2013 | Planning permission granted |
| 31 December 2013 | Construction started |
| 31 March 2014 | Operational |
Project details
- Technology
- solar farm
- Capacity
- 15.6 MW
- Status (REPD)
- operational
- Record last updated
- 2 March 2018
- Operator or applicant
- Hive Energy
- Planning authority
- Torridge
- Planning application reference
- 1/0833/2012/FULM
- Address (REPD)
- Pitworthy Farm Pancrasweek Holsworthy Devon
- Council area (by location)
- Torridge
- Time to decision
- 37 weeks
- REPD reference
- 2013
Who decides
| Applications | Torridge | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 45 | 10,236 |
| Refused | 12 (27%) | 19% |
| Solar refused | 4 of 31 | 12% |
| Onshore wind refused | 6 of 8 | 45% |
| Battery storage refused | 2 of 6 | 16% |
| Median time from submission to decision | 24.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 3 / 7 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Land At Southland Farm (NOR) | solar farm | 5 | abandoned | 3.0 |
| Solar Farm at Land At Monks Farm And Trelana Pyworthy Holsworthy | solar farm | 42 | operational | 3.4 |
| Stoneworthy | battery storage | 49.9 | approved, not built | 3.7 |
| CRINACOTT SOLAR FARM (Pyworthy) | solar farm | 6.7 | operational | 3.9 |
| Pinkworthy Farm, Pyworthy | battery storage | 25 | approved, not built | 4.6 |
| Bradford Solar Park | solar farm | 5.3 | operational | 4.6 |
| Derriton Fields Solar Farm | solar farm | 11.8 | operational | 4.7 |
| East Langford Farm | solar farm | 5 | operational | 5.4 |
| Land At Woodlands Farm | solar farm | 8 | refused | 5.5 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8214, -4.4275).