Energy Projects Near You

Pitworthy Farm Solar Park (15.6 MW)

Pitworthy Farm Solar Park is a 15.6 MW solar farm project in Torridge, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2014; the record was last updated on 2 March 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15.6 MWsolar farm
operationalstatus in REPD
2 March 2018record last updated
Torridgecouncil area

Planning timeline

DateStage
18 October 2012Application submitted
4 July 2013Planning permission granted
31 December 2013Construction started
31 March 2014Operational

Project details

Technology
solar farm
Capacity
15.6 MW
Status (REPD)
operational
Record last updated
2 March 2018
Operator or applicant
Hive Energy
Planning authority
Torridge
Planning application reference
1/0833/2012/FULM
Address (REPD)
Pitworthy Farm Pancrasweek Holsworthy Devon
Council area (by location)
Torridge
Time to decision
37 weeks
REPD reference
2013

Who decides

ApplicationsTorridgeUK
Decided applications (solar, wind, battery)4510,236
Refused12 (27%)19%
Solar refused4 of 3112%
Onshore wind refused6 of 845%
Battery storage refused2 of 616%
Median time from submission to decision24.1 weeks17.0 weeks
Appeals lodged / allowed3 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land At Southland Farm (NOR)solar farm5abandoned3.0
Solar Farm at Land At Monks Farm And Trelana Pyworthy Holsworthysolar farm42operational3.4
Stoneworthybattery storage49.9approved, not built3.7
CRINACOTT SOLAR FARM (Pyworthy)solar farm6.7operational3.9
Pinkworthy Farm, Pyworthybattery storage25approved, not built4.6
Bradford Solar Parksolar farm5.3operational4.6
Derriton Fields Solar Farmsolar farm11.8operational4.7
East Langford Farmsolar farm5operational5.4
Land At Woodlands Farmsolar farm8refused5.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8214, -4.4275).