Derriton Fields Solar Farm (11.8 MW)

Derriton Fields Solar Farm is an 11.8 MW solar farm project in Torridge, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2014; the record was last updated on 30 April 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11.8 MWsolar farm
operationalstatus in REPD
30 April 2014record last updated
Torridgecouncil area

Planning timeline

DateStage
6 November 2012Application submitted
5 February 2013Planning permission granted
13 January 2014Construction started
31 March 2014Operational

Project details

Technology
solar farm
Capacity
11.8 MW
Status (REPD)
operational
Record last updated
30 April 2014
Operator or applicant
Sunsave 12 (Derriton Fields) Limited./ Vogt solar
Planning authority
Torridge
Planning application reference
1/0978/2012/FULM
Address (REPD)
Derriton Fields Farm Holsworthy Devon
Council area (by location)
Torridge
Time to decision
13 weeks
REPD reference
1648

Who decides

ApplicationsTorridgeUK
Decided applications (solar, wind, battery)4510,236
Refused12 (27%)19%
Solar refused4 of 3112%
Onshore wind refused6 of 845%
Battery storage refused2 of 616%
Median time from submission to decision24.1 weeks17.0 weeks
Appeals lodged / allowed3 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Stoneworthybattery storage49.9approved, not built2.3
CRINACOTT SOLAR FARM (Pyworthy)solar farm6.7operational2.7
Solar Farm at Land At Monks Farm And Trelana Pyworthy Holsworthysolar farm42operational3.9
Land At Woodlands Farmsolar farm8refused4.3
Pitworthy Farm Solar Parksolar farm15.6operational4.7
Land At Southland Farm (NOR)solar farm5abandoned4.7
Foxcombe Farm Solar Parksolar farm5operational5.2
Pinkworthy Farm, Pyworthybattery storage25approved, not built5.2
Bradford Solar Parksolar farm5.3operational5.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8026, -4.3678).