Energy Projects Near You

Solar, wind and battery projects near Launceston (PL15)

10 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PL15 (Cornwall): 2 are waiting for a planning decision, 1 approved but not yet running, 4 operational. The largest live scheme is Cold Northcott Windfarm Repowering (22 MW wind farm, application submitted on 27 November 2023, no decision recorded; REPD status may be out of date), 1.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10projects within 10 km
2awaiting a decision
1approved, not running
4operational

Projects within 10 km of PL15

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Cold Northcott Windfarm Repoweringwind farmwind farm22application submitted may be out of dateupdated Dec 2023Nov 2023—Dec 2023Cornwall1.4
Link Roadbattery storagebattery storage3approved, not built may be out of dateupdated Mar 2023Sep 2022granted Nov 2022Mar 2023Cornwall2.5
Tinny Hall Solar Farmsolar farmsolar farm1.5application withdrawnupdated Aug 2017Mar 2012—Aug 2017Cornwall5.2
Hexworthy Solar Parksolar farmsolar farm5.4abandonedupdated May 2017Apr 2013granted Jul 2013May 2017Cornwall6.1
Lidcott, Laneastwind turbinewind turbine1application submittedupdated Dec 2025Nov 2025—Dec 2025Cornwall6.8
Parabel North Beer Solar Farmsolar farmsolar farm6.8operationalupdated Dec 2013Nov 2012granted Feb 2013Dec 2013Cornwall7.6
Winsdon Farmsolar farmsolar farm5operationalupdated Nov 2015Oct 2010granted Jan 2011Nov 2015Cornwall8.1
Grange Farm (Cornwall)solar farmsolar farm5operationalupdated Sep 2015Mar 2011granted May 2011Sep 2015Cornwall8.9
Tredown Solar Farmsolar farmsolar farm1.2operationalupdated Feb 2014Mar 2012granted Mar 2013Feb 2014West Devon9.3
Trew Farmsolar farmsolar farm1.5abandonedupdated Apr 2014Mar 2012granted Oct 2012Apr 2014Cornwall9.4

Distance from the average position of the PL15 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm700400
Wind farm1100022
Wind turbine110001
Battery storage101003

MW in pipeline: pending, approved and under-construction capacity.

How Cornwall decides solar, wind and battery applications

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

All projects in Cornwall

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PL15, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.