Energy Projects Near You

Hexworthy Solar Park (5.4 MW)

Hexworthy Solar Park is a 5.4 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 26 May 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.4 MWsolar farm
abandonedstatus in REPD
26 May 2017record last updated
Cornwallcouncil area

Planning timeline

DateStage
10 April 2013Application submitted
8 July 2013Planning permission granted

Project details

Technology
solar farm
Capacity
5.4 MW
Status (REPD)
abandoned
Record last updated
26 May 2017
Operator or applicant
Lightsource Renewable Energy
Planning authority
Cornwall
Planning application reference
PA13/03036
Address (REPD)
Hexworthy Barton, Lawhitton, Launceston, Cornwall
Council area (by location)
Cornwall
Time to decision
13 weeks
REPD reference
1539

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cold Northcott Windfarm Repoweringwind farm22application submitted4.7
Trefinnick Farmsolar farm5operational7.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.6054, -4.3229).