Energy Projects Near You

Solar, wind and battery projects near Torrington (EX38)

23 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EX38 (Torridge): 4 are waiting for a planning decision, 6 approved but not yet running, 10 operational. The largest live scheme is Gammaton Barton Farm, Alverdiscott (100 MW battery storage, approved on 17 July 2025, not yet built), 7.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

23projects within 10 km
4awaiting a decision
6approved, not running
10operational

Projects within 10 km of EX38

Projects of 1 MW and more (17)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Week Farm Solar Parksolar farmsolar farm3.3operationalupdated Apr 2014Apr 2013granted Jul 2013Apr 2014Torridge2.5
Darracott Moorwind farmwind farm2.6operationalupdated Jun 2018Jul 2002granted May 2004Jun 2018Torridge3.9
Deep Moor Landfill Sitesolar farmsolar farm2operationalupdated Jun 2018Mar 2016granted Feb 2017Jun 2018Torridge4.8
Knockworthy Farmsolar farmsolar farm3.5operationalupdated Jul 2018Aug 2012granted Nov 2012Jul 2018Torridge5.0
Cleave Farm Solar Parksolar farmsolar farm4.7operationalupdated Apr 2014Nov 2012granted Feb 2013Apr 2014Torridge6.7
North Devon Wind Farmwind farmwind farm7.5refusedupdated Feb 2015Apr 2013refused Feb 2015Feb 2015Torridge7.0
Gammaton Moor Solar farmsolar farmsolar farm32operationalupdated Jun 2026Sep 2021granted Apr 2022Jun 2026Torridge7.0
Gammaton Barton Farm, Alverdiscottbattery storagebattery storage100approved, not builtupdated Mar 2026Mar 2025granted Jul 2025Mar 2026Torridge7.2
West Webbery Farm, The Waterbattery storagebattery storage99.4application submittedupdated Feb 2026Dec 2025—Feb 2026Torridge7.7
Southcombe Farmsolar farmsolar farm1.2operationalupdated Apr 2013Aug 2012granted Nov 2012Apr 2013Torridge7.8
Bulworthy Farm, Stoney Crossbattery storagebattery storage50application submittedupdated Sep 2025Jul 2025—Sep 2025Torridge8.0
Bulworthy Farm, Stoney Crosssolar farmsolar farm49.9application submittedupdated Sep 2025Jul 2025—Sep 2025Torridge8.0
Beaford Brook Solar Parksolar farmsolar farm5.2operationalupdated Jun 2013Jul 2012granted Dec 2012Jun 2013Torridge8.4
Galsworthy Wind Parkwind farmwind farm9.2operationalupdated Dec 2014Apr 2008granted Sep 2008Dec 2014Torridge8.8
Bulkworthy Solar Parksolar farmsolar farm5approved, not built may be out of dateupdated Aug 2020Dec 2015granted May 2016Aug 2020Torridge9.0
Deptford Farm, Ebberley Hill Solar Farmsolar farmsolar farm27.8approved, not builtupdated Feb 2026Dec 2023refused Jul 2024Feb 2026Torridge9.5
Sedborough Farmwind farmwind farm2application withdrawnupdated May 2008Mar 2008—May 2008Torridge9.9
Smaller schemes under 1 MW, mostly rooftop solar (6)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Huxhill Farm, Weare Giffordwind turbinewind turbine0.2application submittedupdated May 2026Apr 2026—May 2026Torridge5.2
Chubb Roadrooftop solarrooftop solar0.1operationalupdated Jan 2022Jan 2022granted Apr 2022Jan 2022Torridge8.0
Ford Rise - Micro Energy Storagebattery storagebattery storage0.2application withdrawnupdated Apr 2025Feb 2025—Apr 2025Torridge8.4
Horwoodsolar farmsolar farm—approved, not built may be out of dateupdated Apr 2022Mar 2022granted May 2022Apr 2022North Devon9.2
Kingsley School, Northdown Roadrooftop solarrooftop solar0.4approved, not builtupdated Apr 2023Jan 2023granted Mar 2023Apr 2023Torridge9.4
Deptford Farm, Ebberley Hillbattery storagebattery storage—approved, not builtupdated Feb 2026Dec 2023refused Jul 2024Feb 2026Torridge9.5

Distance from the average position of the EX38 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm11137082.7
Rooftop solar201100.4
Wind farm400210
Wind turbine110000.2
Battery storage52200249

MW in pipeline: pending, approved and under-construction capacity.

How Torridge decides solar, wind and battery applications

ApplicationsTorridgeUK
Decided applications (solar, wind, battery)4510,236
Refused12 (27%)19%
Solar refused4 of 3112%
Onshore wind refused6 of 845%
Battery storage refused2 of 616%
Median time from submission to decision24.1 weeks17.0 weeks
Appeals lodged / allowed3 / 7—

All projects in Torridge

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near EX38, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.