Energy Projects Near You

Solar, wind and battery projects near Umberleigh (EX37)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EX37 (North Devon): 5 approved but not yet running, 3 operational. The largest live scheme is Coldharbour Farm, Ashreigney (50 MW solar farm, approved on 19 September 2023, not yet built), 9.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
0awaiting a decision
5approved, not running
3operational

Projects within 10 km of EX37

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Deptford Farm, Ebberley Hill Solar Farmsolar farmsolar farm27.8approved, not builtupdated Feb 2026Dec 2023refused Jul 2024Feb 2026Torridge5.5
Kingsland Barton Solar Farmsolar farmsolar farm5operationalupdated Dec 2014Jun 2013granted Oct 2013Dec 2014North Devon7.6
Beaford Brook Solar Parksolar farmsolar farm5.2operationalupdated Jun 2013Jul 2012granted Dec 2012Jun 2013Torridge8.7
Coldharbour Farm, Ashreigneysolar farmsolar farm50approved, not builtupdated Jun 2026Jul 2021granted Sep 2023Jun 2026Torridge9.3
Deep Moor Landfill Sitesolar farmsolar farm2operationalupdated Jun 2018Mar 2016granted Feb 2017Jun 2018Torridge9.9
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Wixland Farm Solar Farmsolar farmsolar farm0.6approved, not builtupdated Jul 2024Nov 2023granted Jun 2024Jul 2024North Devon3.4
Deptford Farm, Ebberley Hillbattery storagebattery storage—approved, not builtupdated Feb 2026Dec 2023refused Jul 2024Feb 2026Torridge5.5
Bucknell Way, Hacche Lane -Battery Energy Storagebattery storagebattery storage0.2approved, not builtupdated Jan 2025Aug 2024granted Dec 2024Jan 2025North Devon9.6

Distance from the average position of the EX37 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm6033078.4
Battery storage202000.2

MW in pipeline: pending, approved and under-construction capacity.

How North Devon decides solar, wind and battery applications

ApplicationsNorth DevonUK
Decided applications (solar, wind, battery)3710,236
Refused9 (24%)19%
Solar refused4 of 2612%
Onshore wind refused5 of 645%
Battery storage refused0 of 516%
Median time from submission to decision23.3 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

All projects in North Devon

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.