Energy Projects Near You

Solar, wind and battery projects near Chulmleigh (EX18)

2 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EX18 (Mid Devon): 2 approved but not yet running. The largest live scheme is Coldharbour Farm, Ashreigney (50 MW solar farm, approved on 19 September 2023, not yet built), 6.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

2projects within 10 km
0awaiting a decision
2approved, not running
0operational

Projects within 10 km of EX18

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Coldharbour Farm, Ashreigneysolar farmsolar farm50approved, not builtupdated Jun 2026Jul 2021granted Sep 2023Jun 2026Torridge6.8
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Woodterrill Farmsolar farmsolar farm0.2approved, not built may be out of dateupdated Nov 2022Sep 2022granted Oct 2022Nov 2022Torridge5.3

Distance from the average position of the EX18 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm2020050.2

MW in pipeline: pending, approved and under-construction capacity.

How Mid Devon decides solar, wind and battery applications

ApplicationsMid DevonUK
Decided applications (solar, wind, battery)3910,236
Refused13 (33%)19%
Solar refused11 of 3412%
Onshore wind refused1 of 145%
Battery storage refused1 of 416%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

All projects in Mid Devon

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near EX18, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.