Energy Projects Near You

Solar, wind and battery projects near Okehampton (EX20)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EX20 (West Devon): 1 is waiting for a planning decision, 4 approved but not yet running, 1 operational. The largest live scheme is North Tawton Primary Substation (30 MW battery storage, approved on 3 November 2021, not yet built; REPD status may be out of date), 8.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
1awaiting a decision
4approved, not running
1operational

Projects within 10 km of EX20

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Hillsmoor Solar Farmsolar farmsolar farm1.2operationalupdated Aug 2017Jun 2014granted Oct 2014Aug 2017West Devon8.2
Land Adjacent to Taw Valley Creamerysolar farmsolar farm22refusedupdated May 2016Oct 2014refused Jan 2016May 2016West Devon8.3
North Tawton Solar Farmsolar farmsolar farm5refusedupdated Aug 2011Feb 2011refused May 2011Aug 2011West Devon8.4
North Tawton Primary Substationbattery storagebattery storage30approved, not built may be out of dateupdated Nov 2021Jun 2021granted Nov 2021Nov 2021West Devon8.9
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Forthglade Foods, Dartmoor Viewrooftop solarrooftop solar0.9approved, not builtupdated Nov 2022Aug 2022granted Oct 2022Nov 2022West Devon3.2
Hatchmoor Industrial Estate, Hatherleigh Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Nov 2025Jan 2025refused Apr 2025Nov 2025West Devon8.2
Taw Valley Creameryrooftop solarrooftop solar0.2approved, not builtupdated Jan 2022Nov 2021granted Jan 2022Jan 2022West Devon8.9
The Barton Energy Storage Facilitybattery storagebattery storage0.2application submittedupdated Nov 2024Oct 2024—Nov 2024West Devon9.0

Distance from the average position of the EX20 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm300120
Rooftop solar202001.1
Battery storage3120030.4

MW in pipeline: pending, approved and under-construction capacity.

How West Devon decides solar, wind and battery applications

ApplicationsWest DevonUK
Decided applications (solar, wind, battery)1810,236
Refused7 (39%)19%
Solar refused3 of 1212%
Onshore wind refused3 of 345%
Battery storage refused1 of 316%
Median time from submission to decision19.2 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

All projects in West Devon

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near EX20, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.